640 N SALTAIR AVE 90049

Certificate Information: 640 N SALTAIR AVE 90049

Application / Permit
23020-30000-01056
Plan Check / Job No.
B23WL01363
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
New detached trellised roof patio cover at rear of the lot
Permit Issued
Issued on 9/27/2023
Issuing Office
West Los Angeles
Current Status
Issued on 9/27/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/22/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 REZA HAGHIGHAT
Corrections Issued 6/28/2023 CHIHARU SUZUKI
Quality Review Completed 6/28/2023 CHIHARU SUZUKI
Building Plans Picked Up 6/28/2023 APPLICANT
Applicant returned to address corrections 9/19/2023 REZA HAGHIGHAT
Plan Check Approved 9/27/2023 REZA HAGHIGHAT
Issued 9/27/2023 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/9/2023 REZA HAGHIGHAT

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403
Engineer Rowlands,, James; Lic. No.: GE740 10954 SANTA MONICA BLVD      LOS ANGELES, CA 90025
Geologist Nguyen,, An; Lic. No.: EG2468 5913 SATURN STREET      LOS ANGELES, CA 90035

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/10/2023 Approved RYAN BARNES
Excavation/Setback/Form/Re-Bar 10/26/2023 No Access for Inspection RYAN BARNES
Piling/Pier/Caisson 10/31/2023 Conditional Approval RYAN BARNES
Final 12/19/2023 Not Ready for Inspection RYAN BARNES
Footing/Foundation/Slab 12/19/2023 Not Ready for Inspection RYAN BARNES
Green Building Final 12/19/2023 Approved RYAN BARNES
Green Building Rough 12/19/2023 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Approved RYAN BARNES
Smoke Detectors 12/19/2023 Not Ready for Inspection RYAN BARNES
Verify Sprinkler Sign Off 12/19/2023 Approved RYAN BARNES
Wood Frame 12/19/2023 Approved RYAN BARNES
Final 1/9/2024 Conditional Approval RYAN BARNES
Footing/Foundation/Slab 1/9/2024 Approved RYAN BARNES
Smoke Detectors 1/9/2024 Approved RYAN BARNES