341 S ANITA AVE 90049

Certificate Information: 341 S ANITA AVE 90049

Application / Permit
23020-30000-00744
Plan Check / Job No.
B23WL00928
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW RETAINING WALL AT REAR OF LOT. L= 176 FT. Hmax= 6'-0"
Permit Issued
Issued on 6/12/2023
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 3/6/2025

Permit Application Status History

Submitted 4/16/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 HOOMAN HAJIZADEH
Corrections Issued 5/16/2023 HOOMAN HAJIZADEH
Quality Review Completed 5/26/2023 CHIHARU SUZUKI
Building Plans Picked Up 5/30/2023 APPLICANT
Plan Check Approved 6/7/2023 SERGIO SILVA
Issued 6/12/2023 APPLICANT
Permit Finaled 3/5/2025 JOHNNY MIRANDA

Permit Application Clearance Information

Construction within easement Cleared 5/23/2023 TORI CHEN
Grading Pre-Inspection Cleared 6/5/2023 HOOMAN HAJIZADEH

Contact Information

Contractor Blue Label Construction Inc; Lic. No.: 972011-B 2632 WILSHIRE BLVD #363      SANTA MONICA, CA 90403
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Naraghi-Arani,, Kamran; Lic. No.: C40985 30423 CANWOOD ST STE 223      AGOURA HILLS, CA 91301
Engineer Rogers,, Jerome Alan; Lic. No.: L5336 135 N SAN GABRIEL AVE 100      SAN GABRIEL, CA 91775
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Landscape Architect , ; Lic. No.: LA2898       ,

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/20/2023 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 6/21/2023 Partial Approval CHARLES POWELL
Masonry Wall/Backfill 6/28/2023 Approved CHARLES POWELL
Deputy Reinf. Masonry 6/29/2023 Approved CHARLES POWELL
Deputy Reinf. Concrete 2/3/2025 Conditional Approval MATTHEW JENKINS
Footing/Foundation/Slab 2/3/2025 Partial Approval MATTHEW JENKINS
Deputy Reinf. Concrete 2/4/2025 Conditional Approval MATTHEW JENKINS
Deputy Reinf. Masonry 2/11/2025 Conditional Approval MATTHEW JENKINS
Masonry Wall/Backfill 2/11/2025 Partial Approval MATTHEW JENKINS
Final 3/5/2025 Permit Finaled JOHNNY MIRANDA