12124 W PACIFIC AVE 90066
Certificate Information: 12124 W PACIFIC AVE 90066
- Application / Permit
- 23020-30000-00572
- Plan Check / Job No.
- B23WL00754
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- temporary shoring fo new apartment building
- Permit Issued
- Issued on 1/30/2026
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/30/2026
Permit Application Status History
| Submitted | 3/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2023 | KAVIAN REFAHI |
| Corrections Issued | 4/9/2023 | KAVIAN REFAHI |
| Quality Review Completed | 4/10/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 4/10/2023 | APPLICANT |
| Green Plans Picked Up | 4/10/2023 | APPLICANT |
| Applicant returned to address corrections | 5/30/2024 | KAVIAN REFAHI |
| Plan Check Approved | 1/30/2026 | KAVIAN REFAHI |
| Issued | 1/30/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2024 | DARIN LAM |
| Excavation more than 5-ft deep | Cleared | 5/30/2024 | CALOSHA APPROVED |
| Work Adjacent to Public Way | Cleared | 1/26/2026 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Dejban,, Masoud; Lic. No.: S2521 | 17200 VENTURA BLVD STE 213A ENCINO, CA 91316 |
| Engineer | Kimura,, Jason Edward; Lic. No.: C42389 | 1625 JUNIPER AVE TORRANCE, CA 90503 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/3/2026 | Approved | PAUL DAVIDSON |
| Deputy Grading | 4/22/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Grading | 4/23/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Grading | 4/24/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Grading | 4/27/2026 | Conditional Approval | FARHAD DADBIN |
| Deputy Grading | 4/28/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Grading | 4/29/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Grading | 4/30/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Grading | 5/1/2026 | Conditional Approval | PAUL DAVIDSON |