16601 W PEQUENO PL 90272

Certificate Information: 16601 W PEQUENO PL 90272

Application / Permit
23020-20000-01845
Plan Check / Job No.
B23VN12888
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW RETAINING WALL. HEIGHT = 3' : LENGTH = 131'
Permit Issued
Issued on 5/28/2025
Issuing Office
Valley
Current Status
Issued on 5/28/2025

Permit Application Status History

Submitted 9/21/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 VAHAN JIVALAGIAN
Corrections Issued 10/5/2023 VAHAN JIVALAGIAN
Quality Review Completed 10/12/2023 OMID HEDAYAT
Building Plans Picked Up 10/17/2023 APPLICANT
Applicant returned to address corrections 10/31/2023 VAHAN JIVALAGIAN
Applicant returned to address corrections 2/28/2025 VAHAN JIVALAGIAN
Plan Check Approved 5/28/2025 VAHAN JIVALAGIAN
Issued 5/28/2025 APPLICANT

Permit Application Clearance Information

Coastal Zone Cleared 11/2/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 11/2/2023 NELSON RODRIGUEZ
ZA Case Cleared 11/2/2023 NELSON RODRIGUEZ
Grading Pre-Inspection Cleared 3/18/2025 VAHAN JIVALAGIAN
Eng Process Fee Ord 176,300 Cleared 5/27/2025 DIANA RENTERIA
Miscellaneous Cleared 5/27/2025 DIANA RENTERIA

Contact Information

Contractor Picture Build; Lic. No.: 990772-B 12410 FOOTHILL BLVD UNIT U      SYLMAR, CA 91342
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024
Geologist Van, Meter, James L.; Lic. No.: EG2031 6634 VALJEAN AVE      VAN NUYS, CA 91406

Inspector Information

RAMAZANALI ALMASI, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/11/2025 Partial Approval JOHNNY MIRANDA
Deputy Grading 7/15/2025 Conditional Approval JOHNNY MIRANDA
Deputy Grading 7/17/2025 Partial Approval LANNY MERRICK
Deputy Grading 7/18/2025 Conditional Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 7/24/2025 Partial Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 8/4/2025 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 8/4/2025 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 8/5/2025 Conditional Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 8/12/2025 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 8/14/2025 Conditional Approval LANNY MERRICK