559 S BEVERLY GLEN BLVD 90024
Certificate Information: 559 S BEVERLY GLEN BLVD 90024
- Application / Permit
- 23020-20000-01640
- Plan Check / Job No.
- B23VN11443
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- New Retaining wall L=93' , maximum height = 6'. All work done per engineer.
- Permit Issued
- Issued on 10/19/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/21/2025
Permit Application Status History
| Submitted | 8/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | NAREG ATARIAN |
| Corrections Issued | 9/2/2023 | NAREG ATARIAN |
| Quality Review Completed | 9/7/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 9/8/2023 | APPLICANT |
| Applicant returned to address corrections | 9/27/2023 | NAREG ATARIAN |
| Applicant returned to address corrections | 10/13/2023 | NAREG ATARIAN |
| Plan Check Approved | 10/19/2023 | NAREG ATARIAN |
| Issued | 10/19/2023 | APPLICANT |
| Permit Finaled | 8/21/2025 | LANNY MERRICK |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Hilliard J Stuart Inc; Lic. No.: 182031-C-8 | 7136 HASKELL AVENUE SUITE 109 VAN NUYS, CA 91406 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
| Engineer | Rowlands,, James; Lic. No.: GE740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/14/2023 | Partial Inspection | MATTHEW JENKINS |
| Footing/Foundation/Slab | 5/7/2024 | Approved | VASIL MIHALEV |
| Reinforced Masonry Frame | 5/8/2024 | Partial Inspection | MATTHEW JENKINS |
| Special/Order Compliance | 5/8/2024 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 5/10/2024 | Conditional Approval | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 6/27/2024 | Conditional Approval | MATTHEW JENKINS |
| Structural Steel Frame | 6/27/2024 | Partial Inspection | MATTHEW JENKINS |
| Footing/Foundation/Slab | 7/19/2024 | Partial Approval | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 2/20/2025 | Partial Approval | JOHNNY MIRANDA |
| Final | 8/21/2025 | Permit Finaled | LANNY MERRICK |