509 W WASHINGTON BLVD 90015
Certificate Information: 509 W WASHINGTON BLVD 90015
- Application / Permit
- 23020-20000-01582
- Plan Check / Job No.
- B23VN10870
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- ePLAN. TEMPORARY SHORING WITH SOLDIER PILES & LAGGING FOR NEW SEVEN STORY TYPE I-B NEW FRANCHISE AUTOMOBILE SALES ( BUILDING PERMIT # 22010-20000-06171)
- Permit Issued
- Issued on 11/30/2023
- Issuing Office
- Current Status
- Permit Finaled on 3/1/2020
- Certificate of Occupancy
- TCO Issued More Information
Permit Application Status History
| Permit Finaled | 3/1/2020 | JAMES POWERS |
| Submitted | 8/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2023 | GARO TELMI |
| Corrections Issued | 9/7/2023 | GARO TELMI |
| Quality Review Completed | 9/22/2023 | CHAD DOI |
| Applicant returned to address corrections | 10/1/2023 | GARO TELMI |
| Applicant returned to address corrections | 10/17/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/12/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/14/2023 | GARO TELMI |
| Plan Check Approved | 11/22/2023 | GARO TELMI |
| Issued | 11/30/2023 | APPLICANT |
Permit Application Clearance Information
| "D" conditions | Cleared | 9/28/2023 | MAYELA VILLA |
| Community Plan Implem. Overlay | Cleared | 9/28/2023 | MAYELA VILLA |
| Miscellaneous | Cleared | 9/28/2023 | MAYELA VILLA |
| Work Adjacent to Public Way | Cleared | 10/2/2023 | LARRY LEE |
| Metro Rail approval | Cleared | 10/5/2023 | JENNIFER SU |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2023 | AMY LAM |
| Historic Resource Verification | Cleared | 10/10/2023 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 10/10/2023 | YASMINE BASHIRI |
| Community Plan Implem. Overlay | Cleared | 10/18/2023 | ADRIAN SANCHEZ |
| Community Plan Implem. Overlay | Cleared | 10/20/2023 | TAIMOUR TANAVOLI |
| Excavation more than 5-ft deep | Cleared | 10/20/2023 | CALOSHA APPROVED |
| Community Plan Implem. Overlay | Cleared | 11/2/2023 | ADALBERTO VERA |
| Community Plan Implem. Overlay | Cleared | 11/3/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Fults Christopher Lawrence; Lic. No.: 651257-C36 | 1720 WHITTIER AVE COSTA MESA, CA 92627 |
| Engineer | Boyle,, Dylan Joseph; Lic. No.: GE3139 | 102 EAGLE POINT IRVINE, CA 92604 |
| Engineer | Reed,, Roy P; Lic. No.: C80503 | 7727 CAMINITO LILIANA SAN DIEGO, CA 92129 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 12/4/2023 | Partial Approval | JAMES POWERS |
| Deputy Grading | 2/26/2025 | Partial Approval | JAMES POWERS |