714 S HILGARD AVE 90024
Certificate Information: 714 S HILGARD AVE 90024
- Application / Permit
- 23020-20000-01341
- Plan Check / Job No.
- B23VN08966
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- 2 NEW RETAINING WALLS RETAINING WALL 1. L = 22'-6" , HEIGHT = 5'-6" RETAINING WALL 2. L = 19'-5" , HEIGHT = 5'-6"
- Permit Issued
- Issued on 8/14/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/31/2024
Permit Application Status History
| Submitted | 7/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/14/2023 | APPLICANT |
| Corrections Issued | 7/18/2023 | ARTIN ZARUKIAN |
| Plan Check Approved | 7/24/2023 | GIOVANNY CHAVEZ |
| Issued | 8/14/2023 | APPLICANT |
| Permit Finaled | 5/30/2024 | MATTHEW JENKINS |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/17/2023 | KEVIN FULTON |
| Specific Plan | Cleared | 7/17/2023 | KEVIN FULTON |
Contact Information
| Contractor | Design Scapes Inc; Lic. No.: 1070231-B | 2708 WILSHIRE BLVD STE 109 SANTA MONICA, CA 90403 |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/17/2023 | Partial Inspection | MATTHEW JENKINS |
| Pre-Inspection | 9/26/2023 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 11/6/2023 | Partial Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 11/28/2023 | Corrections Issued | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 12/4/2023 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 12/5/2023 | Partial Approval | MATTHEW JENKINS |
| Masonry Wall/Backfill | 12/12/2023 | Partial Inspection | MATTHEW JENKINS |
| Footing/Foundation/Slab | 12/14/2023 | Not Ready for Inspection | MATTHEW JENKINS |
| Footing/Foundation/Slab | 1/5/2024 | Partial Inspection | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 1/8/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 1/9/2024 | Corrections Issued | MATTHEW JENKINS |
| Footing/Foundation/Slab | 1/9/2024 | Partial Inspection | MATTHEW JENKINS |
| Footing/Foundation/Slab | 1/12/2024 | Partial Approval | MATTHEW JENKINS |
| Masonry Wall/Backfill | 1/19/2024 | Partial Inspection | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 1/26/2024 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/27/2024 | No Access for Inspection | ROBERT PINA |
| Final | 3/1/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Reinforced Concrete Frame | 3/18/2024 | Partial Inspection | MATTHEW JENKINS |
| Final | 5/22/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 5/30/2024 | Permit Finaled | MATTHEW JENKINS |