1800 N MICHELTORENA ST 90026

Certificate Information: 1800 N MICHELTORENA ST 90026

Application / Permit
23020-20000-01212
Plan Check / Job No.
B23VN07898
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW 17 LF X 10 FT HIGH RETAINING WALL AND NEW SHORING FOR THE HOUSE , ALL WORK EPR ENGINEERING
Permit Issued
Issued on 7/11/2024
Issuing Office
Metro
Current Status
Issued on 7/11/2024

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 RARES BODEA
Corrections Issued 7/7/2023 RARES BODEA
Quality Review Completed 7/10/2023 STEVEN KIM
Building Plans Picked Up 7/11/2023 APPLICANT
Applicant returned to address corrections 4/11/2024 RARES BODEA
Applicant returned to address corrections 6/4/2024 RARES BODEA
Plan Check Approved 6/18/2024 RARES BODEA
Issued 7/11/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/21/2023 TREVOR QUAN
Tract Map conditions Cleared 7/21/2023 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 7/26/2023 TREVOR QUAN
Grading Pre-Inspection Cleared 6/4/2024 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

LANNY MERRICK, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/18/2024 Partial Inspection HAMIK HARTOUNIAN
Deputy Grading 7/19/2024 Conditional Approval HAMIK HARTOUNIAN
Deputy Grading 7/22/2024 Conditional Approval BRENDAN MORELLI
Pre-Inspection 7/26/2024 Partial Inspection LANNY MERRICK
Piling/Pier/Caisson 7/29/2024 Partial Approval JONATHAN HOM
Deputy Grading 7/31/2024 Approved ALEXANDER HELFER
Piling/Pier/Caisson 7/31/2024 Approved ALEXANDER HELFER
Deputy Grading 8/1/2024 Conditional Approval LANNY MERRICK
Deputy Grading 8/2/2024 Conditional Approval RUSSELL BONVOULOIR
Piling/Pier/Caisson 8/2/2024 Partial Approval RUSSELL BONVOULOIR
Deputy Grading 8/6/2024 Conditional Approval RUSSELL BONVOULOIR
Piling/Pier/Caisson 8/6/2024 Partial Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 11/1/2024 Corrections Issued RUSSELL BONVOULOIR
Piling/Pier/Caisson 11/1/2024 Partial Inspection RUSSELL BONVOULOIR
Pre-Inspection 11/1/2024 Partial Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 11/19/2024 Partial Approval ALEXANDER HELFER
Excavation/Setback/Form/Re-Bar 12/3/2024 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 12/9/2024 Not Ready for Inspection ALEXANDER HELFER