6736 W FOOTHILL BLVD 91042
Certificate Information: 6736 W FOOTHILL BLVD 91042
- Application / Permit
- 23020-20000-00536
- Plan Check / Job No.
- B23VN03343
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Retaining Wall
- Work Description
- Construction of two Retaining Walls for new drive-through Starbucks
- Permit Issued
- Issued on 2/23/2024
- Issuing Office
- Current Status
- Permit Finaled on 2/11/2026
Permit Application Status History
| Submitted | 3/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 4/27/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 5/1/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 8/23/2023 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 2/9/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 2/23/2024 | SERGIO GUTIERREZ |
| Issued | 2/23/2024 | APPLICANT |
| Permit Finaled | 2/11/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/1/2023 | TINA MIRANDA |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2023 | CARLOS AGUILERA |
| Work Adjacent to Public Way | Cleared | 10/3/2023 | LEE GUILBEAUX |
| Disturb/Remove Protected Trees | Cleared | 11/13/2023 | ADALBERTO VERA |
| Miscellaneous | Cleared | 12/4/2023 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 12/4/2023 | JAZMIN ROQUE |
| Comm Cor/Mini-Mall | Cleared | 12/6/2023 | JAZMIN ROQUE |
| Landscape for retaining wall | Cleared | 12/6/2023 | JAZMIN ROQUE |
| Specific Plan | Cleared | 12/6/2023 | JAZMIN ROQUE |
| ZA Case | Cleared | 12/6/2023 | JAZMIN ROQUE |
| GPI Written Notices | Cleared | 2/23/2024 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 2/23/2024 | SERGIO GUTIERREZ |
Contact Information
| Architect | , ; Lic. No.: C38560 | , |
| Contractor | Sipan Contruction Co.; Lic. No.: 676103-B | 3200 LA CRESCENTA AVE SUITE_B GLENDALE, CA 91208 |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Jacoby,, Samuel John; Lic. No.: C74309 | 16842 VON KARMAN AVE STE 150 IRVINE, CA 92606 |
| Engineer | Pachunuri,, Nalin Kumar; Lic. No.: C788970 | , |
| Engineer | Smith,, Randall James; Lic. No.: L5189 | 2935 HENRIETTA AVE LA CRESCENTA, CA 91214 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/17/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 4/18/2024 | Approved | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/18/2024 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/22/2024 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Shotcrete | 4/23/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/17/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/20/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/21/2024 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 6/4/2024 | Partial Approval | JOHN KITCKO |
| Deputy Shotcrete | 6/5/2024 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 6/14/2024 | Conditional Approval | ANDREW DORSO |
| Deputy Shotcrete | 6/14/2024 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 6/18/2024 | Partial Approval | KENNETH ROBERTS |
| Footing/Foundation/Slab | 7/25/2024 | Partial Approval | DANNY RODRIGUEZ |
| Special/Order Compliance | 9/9/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 9/12/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 9/17/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 9/27/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 10/2/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 10/15/2024 | Partial Approval | JOHN KITCKO |
| Special/Order Compliance | 10/22/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 11/8/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 11/18/2024 | Partial Approval | DANNY RODRIGUEZ |
| Final | 2/11/2026 | Permit Finaled | JEFFREY DURAN |