21800 W LOPEZ ST 91364

Certificate Information: 21800 W LOPEZ ST 91364

Application / Permit
23020-20000-00534
Plan Check / Job No.
B23VN03311
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
SUPPLEMENTAL PERMIT TO 16020-20000-02383 TO REVISE RETAINING WALL LAYOUT AND ENGINEERING DETAILS. CHANGE ENGINEER OF RECORD.
Permit Issued
Issued on 5/24/2023
Issuing Office
Valley
Current Status
Issued on 5/24/2023

Permit Application Status History

Submitted 3/16/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 RAPHAEL ROSAS
Corrections Issued 3/28/2023 RAPHAEL ROSAS
Quality Review Completed 3/30/2023 STEVEN KIM
Building Plans Picked Up 3/31/2023 APPLICANT
Applicant returned to address corrections 4/24/2023 RAPHAEL ROSAS
Applicant returned to address corrections 5/12/2023 RAPHAEL ROSAS
Plan Check Approved 5/24/2023 RAPHAEL ROSAS
Issued 5/24/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/5/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/7/2023 ROMAN GUTIERREZ
Grading Pre-Inspection Cleared 5/12/2023 RAPHAEL ROSAS
Landscape for retaining wall Cleared 5/12/2023 NATHAN ROMINE

Contact Information

Contractor Rocha Nuez Abdoh Construction Inc; Lic. No.: 791474-B 28025 DOROTHY DRIVE 100      AGOURA HILLS, CA 91301
Engineer Abbasi,, Talat Abbas; Lic. No.: C36022 2151 HALL CIRCLE      LIVERMORE, CA 94550
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Geologist Hill,, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 10/11/2023 Corrections Issued ROBERT PINA
Deputy Reinf. Concrete 10/24/2023 Approved ROBERT PINA
Deputy Reinf. Concrete 10/31/2023 Approved ROBERT PINA
Deputy Other (see comments) 11/28/2023 Approved MANUEL TEJADA
Footing/Foundation/Slab 11/28/2023 Partial Approval MANUEL TEJADA
Reinforced Concrete Frame 12/12/2023 Partial Approval ROBERT PINA
Deputy Shotcrete 12/13/2023 Approved ROBERT PINA
Reinforced Concrete Frame 12/14/2023 Partial Approval ROBERT PINA
Deputy Drilled-In Anchors 12/18/2023 No Access for Inspection MICHAEL TEMPLE
Deputy Shotcrete 12/18/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Shotcrete 12/18/2023 No Access for Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 12/18/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Reinforced Concrete Frame 12/18/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Masonry Wall/Backfill 1/2/2024 Partial Approval ROBERT PINA
Final 3/24/2026 Corrections Issued MANUEL TEJADA
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Not Required MANUEL TEJADA
Smoke Detectors 3/24/2026 Not Ready for Inspection MANUEL TEJADA
Final 5/6/2026 Corrections Issued MANUEL TEJADA