19230 W SESNON BLVD 91326
Certificate Information: 19230 W SESNON BLVD 91326
- Application / Permit
- 23020-20000-00465
- Plan Check / Job No.
- B23VN02854
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- eplan Modification to Existing Wireless Telecommunications Facility (WTF): -Swap Existing Propane Generator and Tank with New Diesel Generator and Base Fuel Tank -Install (1) 10' x4' Concrete Pad -Install (1) Automatic Transfer Switch -Install (1) Emergency Shut-Off Switch
- Permit Issued
- Issued on 9/21/2023
- Issuing Office
- Current Status
- Permit Finaled on 2/7/2024
Permit Application Status History
| Submitted | 3/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2023 | LUKE GONZALES |
| Corrections Issued | 3/16/2023 | LUKE GONZALES |
| Applicant returned to address corrections | 8/17/2023 | HANS SANTIAGO |
| Plan Check Approved | 8/28/2023 | ANDREW SANTIAGO |
| Issued | 9/21/2023 | APPLICANT |
| Permit Finaled | 12/14/2023 | BRIAN KELLY |
Permit Application Clearance Information
| ZA Case | Cleared | 8/3/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 8/10/2023 | LESLIE PEREZ |
| ZA Case | Cleared | 8/10/2023 | LESLIE PEREZ |
| ZA Case | Cleared | 8/10/2023 | LESLIE PEREZ |
| ZA Case | Cleared | 8/10/2023 | LESLIE PEREZ |
| Grading Pre-Inspection | Cleared | 8/14/2023 | SERGIO VALENZUELA |
| Plan Approval | Cleared | 8/21/2023 | LESLIE PEREZ |
Contact Information
| Contractor | M C Contracting; Lic. No.: 813166-B | 13619 12TH ST UNIT B CHINO, CA 91710 |
| Engineer | Wharton,, Loyall Ainsley; Lic. No.: NA50547 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/15/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 11/15/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 12/14/2023 | Permit Finaled | BRIAN KELLY |
| Final | 12/22/2023 | Partial Inspection | DANNY RODRIGUEZ |