13674 W BAYLISS ROAD 90049
Certificate Information: 13674 W BAYLISS ROAD 90049
- Application / Permit
- 23020-20000-00180
- Plan Check / Job No.
- B22LA26806
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALL (MAX 10' HIGH, 116 LINEAR FEET)
- Permit Issued
- Issued on 10/20/2023
- Issuing Office
- Current Status
- Permit Finaled on 6/30/2025
Permit Application Status History
| Submitted | 1/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2023 | SELLA BENYAMIN |
| Corrections Issued | 1/31/2023 | SELLA BENYAMIN |
| Quality Review Completed | 2/2/2023 | STEVEN KIM |
| Applicant returned to address corrections | 8/18/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 9/12/2023 | SELLA BENYAMIN |
| Plan Check Approved | 9/15/2023 | SELLA BENYAMIN |
| No Progress | 9/19/2023 | SELLA BENYAMIN |
| Plan Check Approved | 9/19/2023 | SELLA BENYAMIN |
| No Progress | 10/19/2023 | SELLA BENYAMIN |
| Plan Check Approved | 10/19/2023 | SELLA BENYAMIN |
| Issued | 10/20/2023 | APPLICANT |
| Permit Finaled | 6/26/2025 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/9/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2023 | JASON NG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| RAMAZANALI ALMASI, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 12/7/2023 | Corrections Issued | CHARLES POWELL |
| Special/Order Compliance | 12/11/2023 | Corrections Issued | JOHNNY MIRANDA |
| Special/Order Compliance | 12/20/2023 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 12/26/2023 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 12/29/2023 | Conditional Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 1/9/2024 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 1/16/2024 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 1/30/2024 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 2/13/2024 | Partial Approval | JOHNNY MIRANDA |
| Piling/Pier/Caisson | 3/12/2024 | Partial Inspection | MATTHEW JENKINS |
| Deputy Reinf. Concrete | 3/14/2024 | Approved | AL GAMBLE |
| Deputy Shotcrete | 6/21/2024 | Conditional Approval | JOHNNY MIRANDA |
| Final | 6/26/2025 | Permit Finaled | JOHNNY MIRANDA |