- Permit Issued
- Issued on 3/14/2023
- Issuing Office
- Current Status
- Permit Finaled on 5/13/2026
Permit Application Status History
| Submitted | 1/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/21/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/23/2023 | STEVEN KIM |
| Building Plans Picked Up | 2/23/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 2/23/2023 | APPLICANT |
| Plan Check Approved | 3/14/2023 | NILOOFAR MEHRAIN |
| Issued | 3/14/2023 | APPLICANT |
| Permit Closed-Status Void | 4/10/2024 | GREGORY POMISH |
| Re-Activate Permit | 12/19/2024 | GREGORY POMISH |
| Permit Finaled | 5/12/2026 | GREGORY POMISH |
Permit Application Clearance Information
| "T" removal | Cleared | 2/24/2023 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2023 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 2/24/2023 | BRENNEN OBETO |
| Sewer availability | Cleared | 2/24/2023 | LEE GUILBEAUX |
| Specific Plan | Cleared | 2/24/2023 | BRENNEN OBETO |
| Tract Map conditions | Cleared | 2/24/2023 | BRENNEN OBETO |
| Tract Map conditions | Cleared | 2/24/2023 | BRENNEN OBETO |
| ZA Case | Cleared | 2/24/2023 | BRENNEN OBETO |
| ZI | Cleared | 2/24/2023 | BRENNEN OBETO |
| DAS Clearance | Cleared | 3/7/2023 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 11/1/2023 | Conditional Approval | JEFFREY FULTON |
| Final | 11/13/2023 | Conditional Approval | JEFFREY FULTON |
| Final | 4/10/2024 | Partial Inspection | GREGORY POMISH |
| Final | 5/12/2026 | Permit Finaled | GREGORY POMISH |
| Pre-Inspection | 5/12/2026 | Approved | GREGORY POMISH |