5729 S LONG BEACH AVE Unit CEL3 90011

Certificate Information: 5729 S LONG BEACH AVE Unit CEL3 90011

Application / Permit
23020-20000-00106
Plan Check / Job No.
B23VN00566
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(15) Telecommunication Transmitter - wireless
Work Description
ePLAN THE PROPOSED PROJECT INCLUDES INSTALLING EQUIPMENT CABINETS AND A GENERATOR ON A PROPOSED CONCRETE PAD AND INSTALLING NEW EQUIPMENT AND MOUNTS ON THE EXISTING TOWER.
Permit Issued
Issued on 12/12/2023
Issuing Office
Current Status
Permit Finaled on 12/24/2025

Permit Application Status History

Submitted 1/19/2023 APPLICANT
Assigned to Plan Check Engineer 2/21/2023 FARSHAD ALIMOHAMADI
Corrections Issued 2/21/2023 FARSHAD ALIMOHAMADI
Quality Review Completed 3/5/2023 GARO TELMI
Applicant returned to address corrections 5/25/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/23/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 12/5/2023 FARSHAD ALIMOHAMADI
Issued 12/12/2023 APPLICANT
Permit Finaled 12/23/2025 DARRYL ARNOLD

Permit Application Clearance Information

Historic Resource Verification Cleared 7/5/2023 MAX LODER
"D" conditions Cleared 9/14/2023 LESLIE PEREZ
Plan Approval Cleared 9/14/2023 LESLIE PEREZ
ZA Case Cleared 9/14/2023 LESLIE PEREZ
CPC Cleared 10/6/2023 YINGSHI HUANG
Community Plan Implem. Overlay Cleared 10/10/2023 HELEN JADALI
Redevelopment Project Area Cleared 10/11/2023 YASMINE BASHIRI
Metro Rail approval Cleared 10/18/2023 JENNIFER SU

Contact Information

Contractor U O S Construction Inc; Lic. No.: 940288-B       ,
Engineer Bhat,, Dinesh; Lic. No.: C53945 1717 S BOULDER AVE STE 300      TULSA, OK 74119

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/22/2024 Approved ALFREDO LOPEZ
Footing/Foundation/Slab 11/22/2024 Approved ALFREDO LOPEZ
Footing/Foundation/Slab 12/17/2024 Not Ready for Inspection RONALD JIMENEZ
Final 9/25/2025 Corrections Issued ALFREDO LOPEZ
Final 12/23/2025 Permit Finaled DARRYL ARNOLD