2512 S CENTINELA AVE 90064
Certificate Information: 2512 S CENTINELA AVE 90064
- Application / Permit
- 23020-10000-02197
- Plan Check / Job No.
- B23LA12062
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- Temporary shoring
- Permit Issued
- Issued on 11/20/2025
- Issuing Office
- Current Status
- Issued on 11/20/2025
Permit Application Status History
| Submitted | 6/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | VU NGUYEN |
| Assigned to Zoning Architect | 7/6/2023 | ERIC ROMERO |
| Corrections Issued | 7/13/2023 | VU NGUYEN |
| Quality Review Completed | 7/13/2023 | EUGENE BARBEAU |
| Plan Check Approved | 11/19/2025 | VU NGUYEN |
| Issued | 11/20/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2024 | JEANIE LAM |
| Excavation more than 5-ft deep | Cleared | 3/28/2024 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 8/25/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 8/25/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 8/25/2025 | JACQUELINE TORRES |
| Work Adjacent to Public Way | Cleared | 9/17/2025 | LARRY LEE |
| Specific Plan | Cleared | 10/9/2025 | JULISSA LOPEZ-HODOYAN |
| CPC | Cleared | 10/23/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 10/23/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 11/6/2025 | JACQUELINE TORRES |
Contact Information
| Contractor | Jeff Mac Construction; Lic. No.: 622633-B | 23717 S HAWTHORNE BLVD # 101 TORRANCE, CA 90505 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 17514 VENTURA BLVD. SUITE 206 ENCINO, CA 91346 |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 2/25/2026 | Partial Approval | VASIL MIHALEV |
| Deputy Grading | 2/27/2026 | No Access for Inspection | VASIL MIHALEV |
| Deputy Grading | 3/3/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Grading | 3/10/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Grading | 3/17/2026 | Conditional Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 4/21/2026 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 4/23/2026 | Partial Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 5/1/2026 | Partial Approval | PAUL DAVIDSON |