2746 N CARMAR DR 90046

Certificate Information: 2746 N CARMAR DR 90046

Application / Permit
23020-10000-02080
Plan Check / Job No.
B23LA20035
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW DETT DECK SUPPORTED BY RETAINING WALL, GRADE BEAMS AND PILES PER SOIL'S REPORT ENGINEERING DESIGN
Permit Issued
Issued on 8/4/2025
Issuing Office
Metro
Current Status
Issued on 8/4/2025

Permit Application Status History

Submitted 10/23/2023 APPLICANT
Assigned to Plan Check Engineer 10/25/2023 SERGIO GUTIERREZ
Corrections Issued 11/1/2023 SERGIO GUTIERREZ
Quality Review Completed 11/3/2023 KEN GILL
Building Plans Picked Up 11/22/2023 APPLICANT
Plan Check Approved 8/4/2025 SERGIO GUTIERREZ
Issued 8/4/2025 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 7/31/2024 JASMIN ASHLEY
Excavation more than 5-ft deep Cleared 9/10/2024 CALOSHA APPROVED
Grading Pre-Inspection Cleared 9/10/2024 SERGIO GUTIERREZ
Specific Plan Cleared 6/13/2025 NATHAN ROMINE
Specific Plan Cleared 6/13/2025 NATHAN ROMINE
GPI Written Notices Cleared 6/25/2025 SERGIO GUTIERREZ

Contact Information

Contractor Alpha Structural Inc; Lic. No.: 663409-B 8334 FOOTHILL BLVD      SUNLAND, CA 91040
Engineer Demers,, Joe Alan; Lic. No.: C71535 894 SANTA MARIA CIRCLE      DUARTE, CA 91010
Engineer Hamilton,, David Thomas; Lic. No.: GE2721 1641 BORDER AVE      TORRANCE, CA 90501
Geologist Haenschke,, Eirik; Lic. No.: EG1597 9616 GIERSON AVE      CHATSWORTH, CA 91311

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/3/2025 Partial Inspection ROY SPAULDING
Excavation/Setback/Form/Re-Bar 11/10/2025 Partial Approval ROY SPAULDING
Piling/Pier/Caisson 11/10/2025 Partial Approval ROY SPAULDING
Deputy Reinf. Concrete 11/13/2025 Conditional Approval ROY SPAULDING
Piling/Pier/Caisson 11/13/2025 Off-Hour Fees Due
Piling/Pier/Caisson 11/13/2025 Partial Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 11/25/2025 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 1/21/2026 Partial Approval DAVID WILLIAMS
Footing/Foundation/Slab 1/26/2026 Approved DAVID WILLIAMS
Wood Frame 2/17/2026 Approved DAVID WILLIAMS