2333-2335 W 4TH ST 90057
Certificate Information: 2333-2335 W 4TH ST 90057
- Application / Permit
- 23020-10000-02068
- Plan Check / Job No.
- B23LA19909
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Grading permit for leveling the vacant lot, and new retaining wall CUT: 684 CY FILL: 96 CY IMPORT: 0 CY EXPORT: 588 CY REMOVAL AND RECOMPACTION: 300 CY
- Permit Issued
- Issued on 3/16/2024
- Issuing Office
- Current Status
- Permit Finaled on 10/15/2024
Permit Application Status History
| Submitted | 10/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2023 | JAD BASMA |
| Corrections Issued | 10/28/2023 | JAD BASMA |
| Quality Review Completed | 10/30/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 12/4/2023 | JAD BASMA |
| Plan Check Approved | 1/10/2024 | JAD BASMA |
| Issued | 3/16/2024 | APPLICANT |
| Permit Finaled | 10/11/2024 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 11/13/2023 | DAVID URITA |
| Redevelopment Project Area | Cleared | 11/13/2023 | DAVID URITA |
| ZI | Cleared | 11/13/2023 | DAVID URITA |
| Grading Pre-Inspection | Cleared | 12/4/2023 | JAD BASMA |
| Abandoned oil well | Cleared | 12/8/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aalam,, Yahya; Lic. No.: NA94318 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 4/2/2024 | Approved | RUSSELL BONVOULOIR |
| Deputy Grading | 5/13/2024 | Approved | JONATHAN HOM |
| Excavation | 5/13/2024 | Partial Inspection | JONATHAN HOM |
| Rough | 5/13/2024 | Partial Inspection | JONATHAN HOM |
| Excavation | 6/26/2024 | Corrections Issued | JONATHAN HOM |
| Excavation | 6/27/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 7/10/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Rough | 7/16/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Special/Order Compliance | 7/23/2024 | Corrections Issued | RUSSELL BONVOULOIR |
| Excavation | 7/31/2024 | Approved | ALEXANDER HELFER |
| Rough | 8/8/2024 | Corrections Issued | JONATHAN HOM |
| Special/Order Compliance | 8/12/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 8/20/2024 | Corrections Issued | RUSSELL BONVOULOIR |
| Approved Compaction Report | 10/10/2024 | Approved | RUSSELL BONVOULOIR |
| Bottom/Toe | 10/11/2024 | Approved | RUSSELL BONVOULOIR |
| Final | 10/11/2024 | Permit Finaled | RUSSELL BONVOULOIR |
| Rough | 10/11/2024 | Approved | RUSSELL BONVOULOIR |