507 N LEWIS ST 90042

Certificate Information: 507 N LEWIS ST 90042

Application / Permit
23020-10000-01977
Plan Check / Job No.
B23LA18984
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
RETAINING WALL REPLACEMENT (REPLACE SOUTH RETAINING WALL). MAX 6'( N.G.) WITH GRADE BEAM ON PILES, WITH SOILS REPORT AND CALCS. 1 OF 2
Permit Issued
Issued on 8/22/2025
Issuing Office
Metro
Current Status
Issued on 8/22/2025

Permit Application Status History

Submitted 10/10/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 TSE MING HUANG
Corrections Issued 10/16/2023 TSE MING HUANG
Quality Review Completed 10/17/2023 EUGENE BARBEAU
Building Plans Picked Up 10/20/2023 APPLICANT
Applicant returned to address corrections 5/8/2024 TSE MING HUANG
Applicant returned to address corrections 6/5/2024 TSE MING HUANG
Applicant returned to address corrections 8/16/2024 TSE MING HUANG
Plan Check Approved 9/9/2024 TSE MING HUANG
Issued 8/22/2025 APPLICANT

Permit Application Clearance Information

Landscape for retaining wall Cleared 1/29/2024 JAZMIN ROQUE
Encroachment in public way Cleared 1/30/2024 KATHERINE MENDOZA
Eng Process Fee Ord 176,300 Cleared 2/9/2024 CELINA MORENO
Trees in Parkway Cleared 2/15/2024 ADALBERTO VERA
Work Adjacent to Public Way Cleared 3/21/2024 LARRY LEE
GPI Written Notices Cleared 9/9/2024 TSE MING HUANG

Contact Information

Contractor Alpha Structural Inc; Lic. No.: 663409-B 8334 FOOTHILL BLVD      SUNLAND, CA 91040
Engineer Aparicio,, Daniel Gonzalo; Lic. No.: C92121 19332 AVENIDA DEL SOL      WALNUT, CA 91789
Engineer Sunna,, Nadim; Lic. No.: GE3172 27035 MARISCAL LN      MISSION VIEJO, CA 92691

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/26/2025 Not Ready for Inspection RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 10/10/2025 Approved RAMAZANALI ALMASI
Piling/Pier/Caisson 10/10/2025 Approved RAMAZANALI ALMASI
Masonry Wall/Backfill 10/17/2025 Partial Approval RAMAZANALI ALMASI
Masonry Wall/Backfill 10/22/2025 Partial Approval RAMAZANALI ALMASI
Deputy Reinf. Masonry 10/29/2025 Conditional Approval RAMAZANALI ALMASI
Special/Order Compliance 12/8/2025 Corrections Issued MICHAEL TEMPLE