2406 S DUXBURY PL 90034

Certificate Information: 2406 S DUXBURY PL 90034

Application / Permit
23020-10000-01897
Plan Check / Job No.
B23LA16892
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Shoring (Temporary)
Work Description
EPLAN: TEMP SHORING FOR (N) RETAINING WALL AND GRADING.
Permit Issued
Issued on 5/10/2024
Issuing Office
Current Status
Permit Finaled on 9/18/2025

Permit Application Status History

Submitted 9/11/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 ADRIANA LOPEZ
Corrections Issued 9/29/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 10/10/2023 TU HUA
Applicant returned to address corrections 1/19/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 4/9/2024 ADRIANA LOPEZ
Applicant returned to address corrections 4/30/2024 ADRIANA LOPEZ
Plan Check Approved 5/6/2024 ADRIANA LOPEZ
Issued 5/10/2024 APPLICANT
Permit Finaled 9/17/2025 LANNY MERRICK

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 4/30/2024 CALOSHA APPROVED
Construction near power lines Cleared 5/3/2024 EDGAR PASCUA
Construction within easement Cleared 5/3/2024 EDGAR PASCUA

Contact Information

Contractor Hillside Repair & Drilling; Lic. No.: 960052-A 933 LAWRENCE STREET      PLACENTIA, CA 92870
Engineer Hoffmayer,, Joseph Julian; Lic. No.: S3935 5043 EVANWOOD AVENUE      OAK PARK, CA 91377
Geologist Triebold,, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 9/5/2024 Conditional Approval MATTHEW JENKINS
Deputy Grading 9/6/2024 Conditional Approval MATTHEW JENKINS
Deputy Grading 9/9/2024 Conditional Approval MATTHEW JENKINS
Deputy Grading 9/10/2024 Conditional Approval MATTHEW JENKINS
Deputy Grading 9/11/2024 Conditional Approval MATTHEW JENKINS
Deputy Reinf. Concrete 9/13/2024 Conditional Approval MATTHEW JENKINS
Piling/Pier/Caisson 9/16/2024 Partial Inspection MATTHEW JENKINS
Piling/Pier/Caisson 9/20/2024 Partial Approval MATTHEW JENKINS
Deputy Reinf. Concrete 9/23/2024 Conditional Approval MATTHEW JENKINS
Piling/Pier/Caisson 9/26/2024 Partial Approval RUSSELL BONVOULOIR
Piling/Pier/Caisson 10/7/2024 Partial Approval MATTHEW JENKINS
Deputy Drilled-In Anchors 10/9/2024 Conditional Approval MATTHEW JENKINS
Piling/Pier/Caisson 10/11/2024 Approved VASIL MIHALEV
Piling/Pier/Caisson 10/17/2024 Not Ready for Inspection AL GAMBLE
Deputy Drilled-In Anchors 11/20/2024 Conditional Approval MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 12/12/2024 Partial Approval MATTHEW JENKINS
Deputy Shotcrete 12/13/2024 Conditional Approval MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 1/23/2025 No Access for Inspection AL GAMBLE
Piling/Pier/Caisson 1/24/2025 Partial Approval AL GAMBLE
Deputy Shotcrete 3/25/2025 No Access for Inspection AL GAMBLE
Final 9/17/2025 Permit Finaled LANNY MERRICK