1810 W 76TH ST 90047

Certificate Information: 1810 W 76TH ST 90047

Application / Permit
23020-10000-01746
Plan Check / Job No.
B23LA16845
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
eplan: Use of Land for the construction of a sculpture park operated by a private entity by right including foundation for the art sculptures, hardscape, plantscape, and planters. Perimeter Walls and Fences to be permitted separately.
Permit Issued
Issued on 5/16/2024
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 RAHEL BEYENE
Corrections Issued 10/6/2023 RAHEL BEYENE
Quality Review Completed 10/19/2023 PRANITA SHAH
Applicant returned to address corrections 12/12/2023 RAHEL BEYENE
Applicant returned to address corrections 2/1/2024 PRANITA SHAH
Plan Check Approved 5/15/2024 PRANITA SHAH
Issued 5/16/2024 APPLICANT
CofO in Progress 3/19/2026 ALFREDO LOPEZ
CofO in Progress 3/20/2026 ALFREDO LOPEZ
CofO in Progress 3/20/2026 ALFREDO LOPEZ
CofO in Progress 3/23/2026 ALFREDO LOPEZ
CofO in Progress 3/23/2026 ALFREDO LOPEZ
Permit Finaled 4/2/2026 ERNESTO CORRAL
CofO Issued 4/2/2026 ERNESTO CORRAL
Permit Finaled 4/2/2026 ERNESTO CORRAL

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 10/17/2023 MANERI ROMAN
Historic Resource Verification Cleared 10/30/2023 ELIZABETH GALLARDO
Redevelopment Project Area Cleared 10/30/2023 ELIZABETH GALLARDO
Low Impact Development (LID) Cleared 2/13/2024 MITESH PATEL

Contact Information

Architect Asamoah,, B Kwesi; Lic. No.: C36558 850 ROSE AVENUE      VENICE, CA 90291
Contractor Taslimi Construction Co Inc; Lic. No.: 475159-B       ,
Engineer Berger,, Phillip Martin; Lic. No.: C13128 601 ARCADIA PL APT 203      NATIONAL CITY, CA 91950
Engineer Zahn,, Michael; Lic. No.: S5054 9119 HARGIS STREET      LOS ANGELES, CA 90034

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/9/2024 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 7/10/2024 Conditional Approval DARRYL ARNOLD
Pre-Inspection 7/19/2024 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 7/24/2024 Approved DARRYL ARNOLD
Reinforced Masonry Frame 7/24/2024 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 7/25/2024 Approved DARRYL ARNOLD
Reinforced Masonry Frame 7/25/2024 Approved DARRYL ARNOLD
Footing/Foundation/Slab 8/1/2024 Not Ready for Inspection DARRYL ARNOLD
Piling/Pier/Caisson 8/1/2024 Conditional Approval DARRYL ARNOLD
Masonry Wall/Backfill 8/14/2024 Approved DARRYL ARNOLD
Deputy Reinf. Masonry 8/16/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 8/19/2024 Conditional Approval DARRYL ARNOLD
Masonry Wall/Backfill 8/19/2024 Approved DARRYL ARNOLD
Footing/Foundation/Slab 9/17/2024 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 10/8/2024 Approved DARRYL ARNOLD
Footing/Foundation/Slab 10/22/2024 Approved DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 8/4/2025 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 9/16/2025 Conditional Approval DARRYL ARNOLD
Pre-Inspection 9/16/2025 Approved DARRYL ARNOLD
Pre-Inspection 9/25/2025 Approved ALFREDO LOPEZ
Final 2/5/2026 Partial Inspection ALFREDO LOPEZ
Final 2/13/2026 Conditional Approval DARRYL ARNOLD
Final 2/19/2026 Conditional Approval ALFREDO LOPEZ
Final 3/11/2026 Conditional Approval DARRYL ARNOLD
Final 3/13/2026 OK to Issue CofO ALFREDO LOPEZ