110 N MAPLETON DR 90077
Certificate Information: 110 N MAPLETON DR 90077
- Application / Permit
- 23020-10000-01689
- Plan Check / Job No.
- B22LA24589
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- ePlan NEW RT WALL
- Permit Issued
- Issued on 10/30/2023
- Issuing Office
- Current Status
- Issued on 10/30/2023
Permit Application Status History
| Submitted | 12/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/11/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/19/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 9/19/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 10/24/2023 | MAHNAZ NOURHASHEMI |
| Issued | 10/30/2023 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/19/2023 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ilasin,, John Lacebal; Lic. No.: C67469 | 1011 OARFISH LN OXNARD, CA 93035 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/8/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 1/9/2024 | Corrections Issued | MATTHEW JENKINS |
| Footing/Foundation/Slab | 1/25/2024 | Partial Approval | JOHNNY MIRANDA |
| Special/Order Compliance | 1/31/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Shotcrete | 2/14/2024 | Approved | VASIL MIHALEV |
| Deputy Shotcrete | 2/14/2024 | Conditional Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 2/14/2024 | Partial Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/6/2024 | Partial Approval | JOHNNY MIRANDA |