2700 N GAFFEY ST 90731
Certificate Information: 2700 N GAFFEY ST 90731
- Application / Permit
- 23020-10000-00816
- Plan Check / Job No.
- B23LA07068
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ePlan PROPOSED EQUIPMENT/PUMP PAD AND PIPE SUPPORTS.
- Permit Issued
- Issued on 8/8/2023
- Issuing Office
- Current Status
- Permit Finaled on 11/8/2023
Permit Application Status History
| Submitted | 4/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | RAPHAEL ROSAS |
| Corrections Issued | 5/10/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 5/17/2023 | STEVEN KIM |
| Applicant returned to address corrections | 6/20/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 7/6/2023 | RAPHAEL ROSAS |
| Issued | 8/8/2023 | APPLICANT |
| Permit Finaled | 11/6/2023 | JOEY BUCHANAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/22/2023 | ROBERT HUGHES |
| "Q" conditions | Cleared | 5/23/2023 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | ANA SORIANO |
| Low Impact Development (LID) | Cleared | 5/30/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/31/2023 | ANA SORIANO |
| DAS Clearance | Cleared | 6/1/2023 | RAPHAEL ROSAS |
Contact Information
| Contractor | Vidal Marco A; Lic. No.: 943211-B | , |
| Engineer | Patil,, Uday Keshav; Lic. No.: GE670 | 4011 P V DRIVE SOUTH RANCHO PALOS VERDES, CA 90275 |
| Engineer | Randig,, Robert Frederick; Lic. No.: C52719 | 2661 MAIN WAY DRIVE LOS ALAMITOS, CA 90720 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/7/2023 | Conditional Approval | AMANUEL BERHE |
| Deputy Reinf. Concrete | 9/7/2023 | Conditional Approval | AMANUEL BERHE |
| Footing/Foundation/Slab | 9/7/2023 | Partial Inspection | AMANUEL BERHE |
| Pre-Inspection | 9/7/2023 | Approved | AMANUEL BERHE |
| Footing/Foundation/Slab | 9/18/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Pre-Inspection | 9/18/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Footing/Foundation/Slab | 9/19/2023 | Not Ready for Inspection | JOEY BUCHANAN |
| Pre-Inspection | 9/19/2023 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 9/25/2023 | Partial Inspection | AMANUEL BERHE |
| Pre-Inspection | 9/25/2023 | Partial Inspection | AMANUEL BERHE |
| Deputy Reinf. Concrete | 9/26/2023 | Conditional Approval | AMANUEL BERHE |
| Deputy Reinf. Concrete | 10/3/2023 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 10/3/2023 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 10/3/2023 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/4/2023 | Approved | JOEY BUCHANAN |
| Final | 11/6/2023 | Permit Finaled | JOEY BUCHANAN |