3022 W WINDSOR AVE 90039

Certificate Information: 3022 W WINDSOR AVE 90039

Application / Permit
23020-10000-00557
Plan Check / Job No.
B23LA05005
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
New retaining wall associated with Pool Permit 22047-10000-00497. RW #1: 55 LF w/ max. 4'-0" high RW #2: 48 LF w/ max. 3'-8" high 1 of 2
Permit Issued
Issued on 1/16/2024
Issuing Office
Metro
Current Status
Permit Finaled on 10/16/2025

Permit Application Status History

Submitted 3/20/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 CHUNG-WEN CHUANG
Corrections Issued 3/29/2023 CHUNG-WEN CHUANG
Quality Review Completed 4/12/2023 CHARLES CHANG
Building Plans Picked Up 4/13/2023 APPLICANT
Applicant returned to address corrections 8/23/2023 CHUNG-WEN CHUANG
Applicant returned to address corrections 8/25/2023 CHUNG-WEN CHUANG
Applicant returned to address corrections 9/18/2023 CHUNG-WEN CHUANG
Plan Check Approved 1/10/2024 CHUNG-WEN CHUANG
Issued 1/16/2024 APPLICANT
Permit Finaled 10/15/2025 RUSSELL BONVOULOIR

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Mg Construction Group Inc; Lic. No.: 1031761-B 8430 SANTA MONICA BLVD #203      WEST HOLLYWOOD, CA 90069
Engineer Song,, Zhenyu Michael; Lic. No.: S5266 12631 IMPERIAL HWY F-230      SANTA FE SPRINGS, CA 90670

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/22/2024 Corrections Issued HAMIK HARTOUNIAN
Piling/Pier/Caisson 5/22/2024 Corrections Issued HAMIK HARTOUNIAN
Piling/Pier/Caisson 5/23/2024 Partial Approval LANNY MERRICK
Pre-Inspection 5/24/2024 Partial Inspection HAMIK HARTOUNIAN
Deputy Reinf. Concrete 5/28/2024 Conditional Approval SCOTT FINNILA
Piling/Pier/Caisson 5/29/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Piling/Pier/Caisson 5/31/2024 Partial Approval ALEXANDER HELFER
Pre-Inspection 5/31/2024 Approved ALEXANDER HELFER
Excavation/Setback/Form/Re-Bar 7/23/2024 Partial Approval LANNY MERRICK
Piling/Pier/Caisson 7/23/2024 Partial Approval LANNY MERRICK
Deputy Reinf. Concrete 7/29/2024 Approved JONATHAN HOM
Piling/Pier/Caisson 8/2/2024 No Access for Inspection RUSSELL BONVOULOIR
Piling/Pier/Caisson 8/5/2024 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 8/14/2024 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 9/10/2024 Conditional Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 10/11/2024 Partial Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 12/11/2024 Partial Approval RUSSELL BONVOULOIR
Masonry Wall/Backfill 1/7/2025 Partial Approval RUSSELL BONVOULOIR
Final 7/10/2025 Not Ready for Inspection RUSSELL BONVOULOIR
Final 10/15/2025 Permit Finaled RUSSELL BONVOULOIR