11263 W DONA LISA DR 91604
Certificate Information: 11263 W DONA LISA DR 91604
- Application / Permit
- 23020-10000-00503
- Plan Check / Job No.
- B22LA26272
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- ePlan (N) RETAINING WALL. 89 ft long and 12 ft max height 2 of 3
- Permit Issued
- Issued on 3/5/2024
- Issuing Office
- Current Status
- Issued on 3/5/2024
Permit Application Status History
| Submitted | 12/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2023 | ADRIANA LOPEZ |
| Corrections Issued | 3/13/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 3/29/2023 | FARUK SEZER |
| Applicant returned to address corrections | 8/21/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 11/15/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 12/18/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 3/5/2024 | ADRIANA LOPEZ |
| Issued | 3/5/2024 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 11/20/2023 | JUDE HERNANDEZ |
| ZI | Cleared | 11/20/2023 | JUDE HERNANDEZ |
| Landscape for retaining wall | Cleared | 12/26/2023 | JUDE HERNANDEZ |
| Excavation more than 5-ft deep | Cleared | 3/5/2024 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 3/5/2024 | ADRIANA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aquino,, Wilson; Lic. No.: C77255 | 15 ROSEMARY CT NOVATO, CA 94945 |
| Engineer | Kazarians,, Ardashes; Lic. No.: C36687 | 1528 CANADA BLVD STE 206 GLENDALE, CA 91208 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
| Geologist | Termeer,, Benjamin Ryan; Lic. No.: EG2687 | 1545 VICTORY BLVD 2ND FL GLENDALE, CA 91201 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/26/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Structural Steel Frame | 8/26/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Approved | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 9/10/2024 | Partial Approval | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 10/25/2024 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 11/13/2024 | Partial Approval | MANUEL TEJADA |
| Masonry Wall/Backfill | 12/6/2024 | Partial Approval | MANUEL TEJADA |
| Final | 1/21/2025 | Not Ready for Inspection | ALEXANDER HELFER |