1719 S SANTEE ST 90015
Certificate Information: 1719 S SANTEE ST 90015
- Application / Permit
- 23020-10000-00435
- Plan Check / Job No.
- B23LA03710
- Group
- Building
- Type
- Nonbldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- eplan: Alteration to (E) telecomunication facility for 20'-0" tower extension with new equipment.
- Permit Issued
- Issued on 6/9/2023
- Issuing Office
- Current Status
- Permit Finaled on 2/2/2024
Permit Application Status History
| Submitted | 3/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2023 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/8/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 5/4/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 5/5/2023 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 5/24/2023 | FARSHAD ALIMOHAMADI |
| Issued | 6/9/2023 | APPLICANT |
| Permit Finaled | 1/26/2024 | JEROME BLACKWOOD |
Permit Application Clearance Information
| "D" conditions | Cleared | 3/17/2023 | KATHERINE RICE |
| Plan Approval | Cleared | 3/17/2023 | KATHERINE RICE |
| Historic Resource Verification | Cleared | 5/4/2023 | MAX LODER |
| Community Plan Implem. Overlay | Cleared | 5/19/2023 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 5/22/2023 | YASMINE BASHIRI |
Contact Information
| Contractor | Innov8 Industries Dba Innov8 Technologies; Lic. No.: 1046959-B | 393 W LA CADENA DR UNIT 15 RIVERSIDE, CA 92501 |
| Engineer | Modi,, Esha; Lic. No.: C92827 | 1312 DIAMOND VALLEY DRIVE CARY, NC 27513 |
| Engineer | Tschetter,, Ryan William; Lic. No.: C89684 | 4090 E BETHENA ST GILBERT, AZ 85295 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 9/6/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 9/13/2023 | Not Ready for Inspection | ALAN MORELOS |
| Footing/Foundation/Slab | 9/13/2023 | Not Ready for Inspection | ALAN MORELOS |
| Pre-Inspection | 9/13/2023 | Not Ready for Inspection | ALAN MORELOS |
| Excavation/Setback/Form/Re-Bar | 9/14/2023 | Not Ready for Inspection | ALAN MORELOS |
| Footing/Foundation/Slab | 9/14/2023 | Not Ready for Inspection | ALAN MORELOS |
| Excavation/Setback/Form/Re-Bar | 9/18/2023 | Approved | ALAN MORELOS |
| Pre-Inspection | 9/26/2023 | Approved | JULIAN CAPUCETTI |
| Final | 1/26/2024 | Permit Finaled | JEROME BLACKWOOD |