1000 W VIN SCULLY AVE 90012

Certificate Information: 1000 W VIN SCULLY AVE 90012

Application / Permit
23020-10000-00410
Plan Check / Job No.
B22LA26975
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Retaining Wall
Work Description
eplan New retaining walls. 1 OF 2
Permit Issued
Issued on 1/7/2025
Issuing Office
Current Status
Permit Finaled on 3/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 MICHAEL LOPEZ
Corrections Issued 3/16/2023 MICHAEL LOPEZ
Quality Review Completed 3/24/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 12/4/2024 MICHAEL LOPEZ
Plan Check Approved 12/31/2024 MICHAEL LOPEZ
Issued 1/7/2025 APPLICANT
Permit Finaled 3/19/2025 RONALD JIMENEZ

Permit Application Clearance Information

ZA Case Cleared 3/16/2023 SPENCER WEJROWSKI
Grading Pre-Inspection Cleared 12/4/2024 ROBERT HUGHES

Contact Information

Contractor ; Lic. No.: 474555-B       ,
Engineer Lay,, Chi-Hung Garry; Lic. No.: GE508 885 S ORANGE GROVE BLVD APT 39      PASADENA, CA 91105
Engineer Rajaskanthan,, Gobishanker; Lic. No.: C93175 2351 MARKS DR      TUSTIN, CA 92782
Engineer Tran,, Thomas Minh; Lic. No.: C82464 919 W. GLENOAKS BLVD., 2ND FLOOR      GLENDALE, CA 91202
Engineer Wilkerson,, Ryan Lee; Lic. No.: S4728 20734 SARDINIA WAY      PORTER RANCH, CA 91326

Inspector Information

JULIAN CAPUCETTI, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/10/2025 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 1/16/2025 Partial Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 1/16/2025 Not Ready for Inspection RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 1/17/2025 Partial Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 1/17/2025 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 1/22/2025 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 1/23/2025 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 2/3/2025 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 2/3/2025 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 2/6/2025 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 2/6/2025 Partial Approval MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 2/6/2025 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 2/11/2025 Partial Inspection RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 2/20/2025 Partial Approval JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 2/25/2025 Partial Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 2/25/2025 Not Ready for Inspection RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 2/26/2025 Partial Approval PAUL BAZERKANIAN
Excavation/Setback/Form/Re-Bar 2/27/2025 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 3/1/2025 Partial Approval CHRISTOPHER BLACKWOOD
Final 3/18/2025 Conditional Approval RONALD JIMENEZ
Final 3/19/2025 Permit Finaled RONALD JIMENEZ