2108 N LINDA FLORA DR 90077

Certificate Information: 2108 N LINDA FLORA DR 90077

Application / Permit
23020-10000-00337
Plan Check / Job No.
B22LA26641
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Shoring (Permanent)
Work Description
ePlan: Permanent shoring on northside of lot. Excavation for new basement level.
Permit Issued
Issued on 2/5/2025
Issuing Office
Current Status
Issued on 2/5/2025

Permit Application Status History

Submitted 1/5/2023 APPLICANT
Assigned to Plan Check Engineer 2/9/2023 RICARDO RAMIREZ
Corrections Issued 2/17/2023 RICARDO RAMIREZ
Quality Review Completed 5/2/2023 MICHAEL PEREZ
Applicant returned to address corrections 10/17/2023 RICARDO RAMIREZ
Applicant returned to address corrections 12/9/2024 RICARDO RAMIREZ
Plan Check Approved 1/24/2025 RICARDO RAMIREZ
Plan Check Approved 2/5/2025 RICARDO RAMIREZ
No Progress 2/5/2025 RICARDO RAMIREZ
Plan Check Approved 2/5/2025 RICARDO RAMIREZ
Issued 2/5/2025 APPLICANT

Permit Application Clearance Information

GPI Written Notices Cleared 12/9/2024 RICARDO RAMIREZ
Grading Pre-Inspection Cleared 12/9/2024 RICARDO RAMIREZ
Miscellaneous Cleared 12/9/2024 RICARDO RAMIREZ
Miscellaneous Cleared 12/9/2024 RICARDO RAMIREZ

Contact Information

Contractor Ecogreen Construction Incorporated; Lic. No.: 938218-B       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/21/2025 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 2/21/2025 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 2/26/2025 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 3/25/2025 Corrections Issued CARLOS MATAMOROS