1312 N MARIPOSA AVE 90027
Certificate Information: 1312 N MARIPOSA AVE 90027
- Application / Permit
- 23020-10000-00047
- Plan Check / Job No.
- B22LA25474
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALL (MAX 5' HIGH, 316.2 LINEAR FEET)
- Permit Issued
- Issued on 8/30/2023
- Issuing Office
- Current Status
- Permit Finaled on 4/5/2024
Permit Application Status History
| Submitted | 12/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2023 | SELLA BENYAMIN |
| Corrections Issued | 1/9/2023 | SELLA BENYAMIN |
| Quality Review Completed | 1/20/2023 | STEVEN KIM |
| Plan Check Approved | 3/2/2023 | SELLA BENYAMIN |
| Plan Check Approved | 5/30/2023 | SELLA BENYAMIN |
| No Progress | 5/30/2023 | SELLA BENYAMIN |
| Plan Check Approved | 5/30/2023 | SELLA BENYAMIN |
| No Progress | 6/6/2023 | SELLA BENYAMIN |
| Plan Check Approved | 6/6/2023 | SELLA BENYAMIN |
| Issued | 8/30/2023 | APPLICANT |
| Permit Finaled | 4/4/2024 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/30/2023 | WALLIE JONG |
Contact Information
| Contractor | Tre Development Llc; Lic. No.: 1075573-B | , |
Inspector Information
| LANNY MERRICK, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/14/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Reinforced Masonry Frame | 11/21/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 12/19/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Masonry Wall/Backfill | 12/28/2023 | Partial Approval | SERGIO VALENZUELA |
| Footing/Foundation/Slab | 1/18/2024 | Partial Approval | CHARLES POWELL |
| Masonry Wall/Backfill | 1/25/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Reinforced Masonry Frame | 1/30/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Final | 2/22/2024 | Conditional Approval | RUSSELL BONVOULOIR |