1219 W 42ND ST 90037
Certificate Information: 1219 W 42ND ST 90037
- Application / Permit
- 23016-70000-43858
- Plan Check / Job No.
- B23SL00123
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached recration room ( 340sft ) attached to garage into an ADU per state law.
- Permit Issued
- Issued on 4/4/2024
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2023 | RICARDO RAMIREZ |
| Corrections Issued | 12/16/2023 | RICARDO RAMIREZ |
| Building Plans Picked Up | 12/21/2023 | APPLICANT |
| Applicant returned to address corrections | 1/9/2024 | LUKE GONZALES |
| Applicant returned to address corrections | 1/16/2024 | LUKE GONZALES |
| Issued | 4/4/2024 | APPLICANT |
| CofO in Progress | 9/22/2025 | SABAS ALONSO |
| Permit Finaled | 9/25/2025 | DEROLD HAUFF |
| CofO Issued | 9/25/2025 | DEROLD HAUFF |
| Permit Finaled | 9/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2024 | JEANIE LAM |
| Sewer availability | Cleared | 1/3/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2024 | JEANIE LAM |
| Construction near power lines | Cleared | 4/4/2024 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/22/2024 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 5/22/2024 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 6/10/2024 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Final | 6/21/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 7/17/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 7/24/2024 | Corrections Issued | SABAS ALONSO |
| Deputy Drilled-In Anchors | 7/31/2024 | Conditional Approval | ALEX COLIN |
| ELECTRICAL-Rough | 8/5/2024 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/14/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 9/10/2024 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 9/10/2024 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 9/10/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 9/10/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/25/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 9/25/2024 | Approved | SABAS ALONSO |
| Insulation | 9/25/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 10/11/2024 | No Access for Inspection | SABAS ALONSO |
| Drywall Nailing | 10/15/2024 | No Access for Inspection | SABAS ALONSO |
| Drywall Nailing | 10/17/2024 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Sewer | 11/12/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 11/12/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 12/23/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 12/23/2024 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 2/28/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 8/29/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 8/29/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Not Required | BARRY HACHE |
| Smoke Detectors | 8/29/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 9/10/2025 | Approved | SABAS ALONSO |
| Final | 9/10/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 9/10/2025 | Approved | SABAS ALONSO |
| Final | 9/17/2025 | OK to Issue CofO | SABAS ALONSO |
| PLUMBING-Final | 9/17/2025 | Approved | SABAS ALONSO |