910 1/2 E 77TH ST 90001
Certificate Information: 910 1/2 E 77TH ST 90001
- Application / Permit
- 23016-70000-40332
- Plan Check / Job No.
- B23SL00107
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached garage at rear of lot into ADU per state law.
- Permit Issued
- Issued on 3/14/2024
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 6/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | RICARDO RAMIREZ |
| Corrections Issued | 11/16/2023 | RICARDO RAMIREZ |
| Plan Check Approved | 3/5/2024 | RICARDO RAMIREZ |
| Issued | 3/14/2024 | APPLICANT |
| CofO in Progress | 6/18/2025 | JOHN QUINTANILLA |
| Permit Finaled | 6/22/2025 | DEROLD HAUFF |
| CofO Issued | 6/22/2025 | DEROLD HAUFF |
| Permit Finaled | 6/22/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/21/2023 | DAVID LOPEZ |
| Sewer availability | Cleared | 11/21/2023 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2023 | DAVID LOPEZ |
| Tenant Habitability Plan | Cleared | 11/29/2023 | HUGO GARRIDO GARZA |
| Construction near power lines | Cleared | 2/23/2024 | RIDWAN HARDY |
Contact Information
| Architect | Garcia,, Hugo; Lic. No.: C33055 | 6429 DOS RIOS ROAD DOWNEY, CA 90240 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/29/2024 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 7/29/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/1/2024 | Partial Approval | MICHAEL LEWIS |
| Sewer | 8/16/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 8/16/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2024 | Partial Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/23/2024 | Approved | MICHAEL LEWIS |
| Rough-Elec/Plmb/HVAC | 9/23/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/25/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 9/25/2024 | Approved | MICHAEL LEWIS |
| Insulation | 9/26/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 10/8/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/9/2024 | Approved | ALEX COLIN |
| Shower Pan | 10/9/2024 | Corrections Issued | ALEX COLIN |
| Shower Pan | 10/16/2024 | Approved | ALEX COLIN |
| Final | 5/1/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Final | 5/1/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 5/1/2025 | SGSOV Not Required | JOHN QUINTANILLA |
| Smoke Detectors | 5/1/2025 | Approved | JOHN QUINTANILLA |
| Final | 5/8/2025 | Corrections Issued | BARRY HACHE |
| Final | 5/12/2025 | OK to Issue CofO | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 5/12/2025 | Approved | JOHN QUINTANILLA |