3417 W 78TH ST 90043
Certificate Information: 3417 W 78TH ST 90043
- Application / Permit
- 23016-70000-36817
- Plan Check / Job No.
- B23SL00082
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU per LAMC 12.22 A.33(c) & (d) at rear of lot. "Comply with department order. Permit to expire 30 days from issuance date."
- Permit Issued
- Issued on 12/19/2023
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 2/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2023 | RICARDO RAMIREZ |
| Corrections Issued | 10/21/2023 | RICARDO RAMIREZ |
| Building Plans Picked Up | 10/26/2023 | APPLICANT |
| Issued | 12/19/2023 | APPLICANT |
| CofO in Progress | 2/26/2024 | JOHN PARKER |
| Permit Finaled | 2/29/2024 | BRUCE TODD |
| CofO Issued | 2/29/2024 | BRUCE TODD |
| Permit Finaled | 2/29/2024 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 12/13/2023 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2023 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 12/13/2023 | AMBER CAMPBELL |
| Sewer availability | Cleared | 12/13/2023 | AMBER CAMPBELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Billings,, Michael; Lic. No.: S6408 | 3415 W 78TH ST LOS ANGELES, CA 90043 |
Inspector Information
| JOHN PARKER, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICHAEL SERETTI, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| HECTOR RODRIGUEZ, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRUCE TODD, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAVIER RAMOS SR, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIAN PODPORA, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/10/2024 | Approved | JOHN PARKER |
| BUILDING-Rough-Frame | 1/31/2024 | Approved | JOHN PARKER |
| Final | 1/31/2024 | Not Ready for Inspection | JOHN PARKER |
| Footing/Foundation/Slab | 1/31/2024 | Approved | JOHN PARKER |
| Green Building Final | 1/31/2024 | Partial Approval | JOHN PARKER |
| Green Building Rough | 1/31/2024 | Approved | JOHN PARKER |
| Rough-Elec/Plmb/HVAC | 1/31/2024 | Approved | JOHN PARKER |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Approved | JOHN PARKER |
| Smoke Detectors | 1/31/2024 | Approved | JOHN PARKER |
| ELECTRICAL-Final | 2/2/2024 | Approved | JOHN PARKER |
| Final | 2/2/2024 | Partial Approval | JOHN PARKER |
| Green Building Final | 2/2/2024 | Approved | JOHN PARKER |
| HVAC-Final | 2/2/2024 | Approved | JOHN PARKER |
| PLUMBING-Final | 2/2/2024 | Approved | JOHN PARKER |
| Final | 2/26/2024 | OK to Issue CofO | JOHN PARKER |