2833 E 4TH ST 90033

Certificate Information: 2833 E 4TH ST 90033

Application / Permit
23016-70000-34503
Plan Check / Job No.
B23SL00074
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Fire damage repair to existing single family dwelling. Repairs include kitchen replacement and bedroom remodels. Structural repairs to damaged roof.
Permit Issued
Issued on 11/16/2023
Issuing Office
South Los Angeles
Current Status
Permit Finaled on 12/5/2024

Permit Application Status History

Submitted 10/5/2023 APPLICANT
Assigned to Plan Check Engineer 10/7/2023 RICARDO RAMIREZ
Corrections Issued 10/7/2023 RICARDO RAMIREZ
Building Plans Picked Up 10/12/2023 APPLICANT
Applicant returned to address corrections 10/24/2023 LAWRENCE QUIRANTE
Issued 11/16/2023 APPLICANT
Permit Finaled 12/5/2024 JUSTIN HAWLEY

Permit Application Clearance Information

Historic Resource Verification Cleared 11/15/2023 DAVID URITA
Redevelopment Project Area Cleared 11/15/2023 DAVID URITA
ZI Cleared 11/15/2023 DAVID URITA

Contact Information

Contractor Property Projects; Lic. No.: 1054123-B 5144 GARDENIA AVE      LONG BEACH, CA 90807
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/27/2023 Approved FREDDIE RIVERA
Pre-Inspection 11/28/2023 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 2/27/2024 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 2/27/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/27/2024 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 2/27/2024 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 4/29/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 4/29/2024 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 5/2/2024 Approved FREDDIE RIVERA
Final 5/2/2024 Partial Inspection FREDDIE RIVERA
Gas Test 5/2/2024 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 5/2/2024 Partial Approval FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Not Ready FREDDIE RIVERA
Insulation 5/10/2024 Approved FREDDIE RIVERA
Drywall Nailing 5/28/2024 Approved JOSH MEISTER
Sewer 6/4/2024 Partial Inspection FREDDIE RIVERA
Interior/Exterior Lathing 7/24/2024 Approved JOSH MEISTER
Shower Pan 7/24/2024 Approved JOSH MEISTER
Final 11/14/2024 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 11/14/2024 Corrections Issued FREDDIE RIVERA
Service/Power Release 11/19/2024 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Not Ready JOHN QUINTANILLA
Final 12/5/2024 Permit Finaled JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 12/5/2024 SGSOV Approved JUSTIN HAWLEY
Service/Power Release 12/5/2024 Approved JUSTIN HAWLEY
Smoke Detectors 12/5/2024 Approved JUSTIN HAWLEY