1546 W 93RD ST 90047
Certificate Information: 1546 W 93RD ST 90047
- Application / Permit
- 23016-70000-25530
- Plan Check / Job No.
- B23SL00034
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert portion of garage and add to create ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 2/6/2024
- Issuing Office
- Current Status
- CofO Issued on 7/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2023 | RICARDO RAMIREZ |
| Corrections Issued | 8/5/2023 | RICARDO RAMIREZ |
| Building Plans Picked Up | 8/10/2023 | APPLICANT |
| Applicant returned to address corrections | 2/1/2024 | RICARDO RAMIREZ |
| Issued | 2/6/2024 | APPLICANT |
| CofO in Progress | 6/27/2025 | WAYNE REGESTER |
| No Progress | 6/29/2025 | DEROLD HAUFF |
| CofO in Progress | 6/29/2025 | DEROLD HAUFF |
| Permit Finaled | 7/13/2025 | DEROLD HAUFF |
| CofO Issued | 7/13/2025 | DEROLD HAUFF |
| Permit Finaled | 7/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/2/2023 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 9/2/2023 | JESSICA OPINION |
| Construction within easement | Cleared | 12/28/2023 | TINA MIRANDA |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 2/2/2024 | JESSICA OPINION |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/13/2024 | Partial Approval | AMIR NAZARIAN |
| Underground Mechanical | 11/21/2024 | Partial Approval | AMIR NAZARIAN |
| Pre-Inspection | 12/19/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 12/30/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 1/6/2025 | Partial Approval | JOSE MACIAS |
| Footing/Foundation/Slab | 1/13/2025 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 2/12/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 6/26/2025 | Approved | WAYNE REGESTER |
| Final | 6/26/2025 | OK to Issue CofO | WAYNE REGESTER |
| Green Building Final | 6/26/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 6/26/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 6/26/2025 | Approved | WAYNE REGESTER |