1207 W PASEO DEL MAR 90731
Certificate Information: 1207 W PASEO DEL MAR 90731
- Application / Permit
- 23016-40000-17152
- Plan Check / Job No.
- B23SP00098
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ALTERATION/REPAIR TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLIING. STRUCTURAL PER WOOD FRAME PRESCRIPTIVE PROVISIONS (WFPP).
- Permit Issued
- Issued on 7/27/2023
- Issuing Office
- San Pedro
- Current Status
- Permit Finaled on 9/4/2024
Permit Application Status History
| Submitted | 5/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | SERGIO SILVA |
| Corrections Issued | 5/25/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 7/13/2023 | SERGIO SILVA |
| Plan Check Approved | 7/27/2023 | SERGIO SILVA |
| Issued | 7/27/2023 | APPLICANT |
| Permit Finaled | 9/4/2024 | PAUL REECE |
Permit Application Clearance Information
| Coastal Zone | Cleared | 7/10/2023 | GEORGIA SMITH |
| Miscellaneous | Cleared | 7/10/2023 | GEORGIA SMITH |
| ZA Case | Cleared | 7/21/2023 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 7/21/2023 | SPENCER WEJROWSKI |
Contact Information
| Contractor | Covington Development Inc; Lic. No.: 634078-B | 11631 ARGYLE DR LOS ALAMITOS, CA 90720 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/1/2023 | Conditional Approval | PAUL REECE |
| Excavation/Setback/Form/Re-Bar | 8/4/2023 | Approved | PAUL REECE |
| Footing/Foundation/Slab | 8/4/2023 | Approved | PAUL REECE |
| Interior/Exterior Lathing | 8/21/2023 | Not Ready for Inspection | PAUL REECE |
| Deputy Drilled-In Anchors | 8/31/2023 | Partial Approval | PAUL REECE |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Partial Approval | PAUL REECE |
| Insulation | 9/7/2023 | Partial Approval | PAUL REECE |
| BUILDING-Rough-Frame | 12/15/2023 | Approved | PAUL REECE |
| ELECTRICAL-Rough | 12/15/2023 | Approved | PAUL REECE |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2023 | Approved | PAUL REECE |
| Gas Test | 12/15/2023 | Approved | PAUL REECE |
| HVAC-Rough | 12/15/2023 | Approved | PAUL REECE |
| PLUMBING-Rough | 12/15/2023 | Approved | PAUL REECE |
| Interior/Exterior Lathing | 12/21/2023 | Approved | KEITH EDGHILL |
| Insulation | 12/28/2023 | Approved | PAUL REECE |
| Drywall Nailing | 1/9/2024 | Approved | PAUL REECE |
| Final | 8/9/2024 | Conditional Approval | PAUL REECE |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Approved | PAUL REECE |
| Smoke Detectors | 8/9/2024 | Approved | PAUL REECE |
| Final | 9/4/2024 | Permit Finaled | PAUL REECE |