8521 N LINDLEY AVE 91325

Certificate Information: 8521 N LINDLEY AVE 91325

Application / Permit
23016-40000-05319
Plan Check / Job No.
B23SP00032
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT (ADU) PER GCS 65852.2(e)(1)(A). CONSTRUCTION PER W.F.P.P.
Permit Issued
Issued on 9/11/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2023 APPLICANT
Assigned to Plan Check Engineer 3/4/2023 LAWRENCE QUIRANTE
Corrections Issued 3/4/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 5/16/2023 APPLICANT
Applicant returned to address corrections 8/10/2023 SERGIO SILVA
Plan Check Approved 8/29/2023 KHUONG TRUONG
Issued 9/11/2023 APPLICANT
CofO in Progress 6/20/2024 KRISTEN BEVERIDGE
CofO in Progress 6/20/2024 KRISTEN BEVERIDGE
CofO in Progress 7/24/2024 KRISTEN BEVERIDGE
Permit Finaled 9/4/2024 JOHN JANSON
CofO Issued 9/4/2024 JOHN JANSON
Permit Finaled 9/4/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/31/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 7/31/2023 TAL SHEMEN
Sewer availability Cleared 7/31/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/11/2023 Approved JOHN KIDWELL
Footing/Foundation/Slab 10/13/2023 Corrections Issued JOHN KIDWELL
BUILDING-Rough-Frame 10/26/2023 Partial Approval JOHN KIDWELL
Green Building Rough 10/26/2023 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 2/9/2024 Approved DAVID SCANTLIN
Green Building Rough 2/9/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 3/14/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 3/14/2024 Corrections Issued KRISTEN CAUSEY
PLUMBING-Rough 3/14/2024 Corrections Issued KRISTEN CAUSEY
Rough-Elec/Plmb/HVAC 3/18/2024 Approved DAVID SCANTLIN
Underground Mechanical 3/18/2024 Approved DAVID SCANTLIN
Insulation 3/20/2024 Approved ARUTYUN MADATYAN
Drywall Nailing 4/1/2024 Approved KRISTEN CAUSEY
Final 6/4/2024 Corrections Issued KRISTEN CAUSEY
Green Building Final 6/4/2024 Not Ready for Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Not Required KRISTEN CAUSEY
Smoke Detectors 6/4/2024 Approved KRISTEN CAUSEY
Final 6/18/2024 Conditional Approval KRISTEN CAUSEY
Green Building Final 6/18/2024 Approved KRISTEN CAUSEY
Final 7/24/2024 OK to Issue CofO KRISTEN CAUSEY
Service/Power Release 7/24/2024 Approved KRISTEN CAUSEY