4226 N BAKMAN AVE 91602
Certificate Information: 4226 N BAKMAN AVE 91602
- Application / Permit
- 23016-30001-23440
- Plan Check / Job No.
- B23WL03113
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Supplemental to pcis # 23016-30000-23440, to change from ADU garage conversion to new ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 3/27/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2023 | RICHARD GARCIA |
| Corrections Issued | 12/23/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 12/26/2023 | APPLICANT |
| Applicant returned to address corrections | 1/11/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 1/12/2024 | CAROLEAN BASMA |
| Issued | 3/27/2024 | APPLICANT |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
| CofO Issued | 12/17/2024 | RUBEN SALAS |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/26/2023 | WALTER RAMIREZ |
| Address approval | Cleared | 12/29/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 12/29/2023 | TAL SHEMEN |
| Low Impact Development (LID) | Cleared | 1/4/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 1/9/2024 | TAL SHEMEN |
| ZI | Cleared | 1/9/2024 | NATHAN ROMINE |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Bems Construction; Lic. No.: 1014009-B | 3121 E CORTO PL APT #1 LONG BEACH, CA 90803 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/3/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 4/12/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 4/30/2024 | Corrections Issued | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/2/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/31/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 5/31/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/31/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 5/31/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 6/6/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 6/6/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/6/2024 | Approved | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 6/6/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/13/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 6/13/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 6/13/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/13/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 6/13/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 6/24/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/3/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 12/3/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Final | 12/3/2024 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 12/3/2024 | Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 12/3/2024 | Approved | CHRISTOPHER ROJAS |