4226 N BAKMAN AVE 91602

Certificate Information: 4226 N BAKMAN AVE 91602

Application / Permit
23016-30001-23440
Plan Check / Job No.
B23WL03113
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Supplemental to pcis # 23016-30000-23440, to change from ADU garage conversion to new ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 3/27/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2023 APPLICANT
Assigned to Plan Check Engineer 12/23/2023 RICHARD GARCIA
Corrections Issued 12/23/2023 RICHARD GARCIA
Building Plans Picked Up 12/26/2023 APPLICANT
Applicant returned to address corrections 1/11/2024 JOHNPAUL ISIP
Plan Check Approved 1/12/2024 CAROLEAN BASMA
Issued 3/27/2024 APPLICANT
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 12/26/2023 WALTER RAMIREZ
Address approval Cleared 12/29/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 12/29/2023 TAL SHEMEN
Sewer availability Cleared 12/29/2023 TAL SHEMEN
Low Impact Development (LID) Cleared 1/4/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 1/9/2024 TAL SHEMEN
ZI Cleared 1/9/2024 NATHAN ROMINE

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Bems Construction; Lic. No.: 1014009-B 3121 E CORTO PL APT #1      LONG BEACH, CA 90803
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/3/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/12/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/30/2024 Corrections Issued JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 5/2/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/2/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/31/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 5/31/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 5/31/2024 Approved CHRISTOPHER ROJAS
Shower Pan 5/31/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/6/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 6/6/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 6/6/2024 Approved CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 6/6/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/13/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 6/13/2024 Approved CHRISTOPHER ROJAS
Insulation 6/13/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/13/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 6/13/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 6/24/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/3/2024 Approved CHRISTOPHER ROJAS
Final 12/3/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Final 12/3/2024 Approved CHRISTOPHER ROJAS
Service/Power Release 12/3/2024 Approved CHRISTOPHER ROJAS
Smoke Detectors 12/3/2024 Approved CHRISTOPHER ROJAS