822 S WARNER AVE 90024

Certificate Information: 822 S WARNER AVE 90024

Application / Permit
23016-30000-44808
Plan Check / Job No.
B23WL03130
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior and exterior remodel to (e) 2-story SFD
Permit Issued
Issued on 5/13/2024
Issuing Office
Metro
Current Status
Permit Finaled on 5/5/2026

Permit Application Status History

Submitted 12/21/2023 APPLICANT
Assigned to Plan Check Engineer 12/27/2023 REZA HAGHIGHAT
Corrections Issued 1/1/2024 REZA HAGHIGHAT
Quality Review Completed 1/8/2024 KAVIAN REFAHI
Building Plans Picked Up 1/11/2024 APPLICANT
Plan Check Approved 4/17/2024 REZA HAGHIGHAT
Issued 5/13/2024 APPLICANT
Permit Finaled 5/5/2026 RYAN SALAZAR

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/27/2024 REZA HAGHIGHAT

Contact Information

Architect Starr,, Nicole Adine; Lic. No.: C25172 731 HALLIDAY AVENUE      LOS ANGELES, CA 90049
Contractor Webb Construction Inc; Lic. No.: 1032560-B 26606 ISABELLA PKWY      SANTA CLARITA, CA 91351
Engineer Kwan,, Denny Chi-Ho; Lic. No.: S4887 5638 NEWFIELDS LN      DUBLIN, CA 94568
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/18/2024 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/18/2024 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 6/21/2024 Approved STEPHANIE SWANSON
Deputy Steel/Welding 12/3/2024 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 12/20/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 1/14/2025 Approved STEPHANIE SWANSON
HVAC-Rough 1/14/2025 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 1/14/2025 Approved STEPHANIE SWANSON
Deputy Steel/Welding 2/6/2025 Conditional Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 2/26/2025 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 2/26/2025 Corrections Issued STEPHANIE SWANSON
Shower Pan 2/26/2025 Approved STEPHANIE SWANSON
Wood Frame 5/1/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 5/13/2025 Approved SEAN HAUPT
HVAC-Rough 5/13/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 5/13/2025 Approved SEAN HAUPT
Insulation 5/22/2025 Approved DANIEL VERA
Drywall Nailing 6/2/2025 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 6/12/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 6/23/2025 Approved DANIEL VERA
Sewer 6/23/2025 Approved DANIEL VERA
Underground Mechanical 6/25/2025 Approved DANIEL VERA
Underground Mechanical 7/3/2025 Approved DANIEL VERA
Pre-Inspection 9/15/2025 Approved DANIEL VERA
Pre-Inspection 9/23/2025 Approved DANIEL VERA
PLUMBING-Rough 11/19/2025 Not Ready for Inspection DANIEL VERA
Pool Piping 11/19/2025 Not Ready for Inspection DANIEL VERA
Underground Mechanical 11/19/2025 Corrections Issued DANIEL VERA
PLUMBING-Rough 12/5/2025 Partial Inspection DANIEL VERA
Pool Piping 12/5/2025 Approved DANIEL VERA
Underground Mechanical 12/5/2025 Approved DANIEL VERA
Pre-Inspection 1/14/2026 Approved CARLOS MATAMOROS
Pre-Inspection 2/12/2026 Partial Inspection ARAM AVEDISIAN
Gas Test 3/4/2026 Approved CARLOS MATAMOROS
PLUMBING-Final 3/4/2026 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 3/20/2026 Corrections Issued CARLOS MATAMOROS
HVAC-Final 3/20/2026 Corrections Issued CARLOS MATAMOROS
Smoke Detectors 3/20/2026 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 4/13/2026 Approved RYAN SALAZAR
HVAC-Final 4/13/2026 Partial Approval RYAN SALAZAR
Smoke Detectors 4/13/2026 Approved RYAN SALAZAR
PLUMBING-Final 4/16/2026 Approved RYAN SALAZAR
Deputy Wood Construction 5/5/2026 Conditional Approval RYAN SALAZAR
Final 5/5/2026 Permit Finaled RYAN SALAZAR
Green Building Final 5/5/2026 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV Approved RYAN SALAZAR