3610 S MIDVALE AVE 212-213 90034

Certificate Information: 3610 S MIDVALE AVE 212-213 90034

Application / Permit
23016-30000-43622
Plan Check / Job No.
B23WL03032
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Fire damage repair to an existing 2-story Apartment Bldg. Repairs are in the garage and units 212 & 213. Replacement of fire damaged framing & finishes. No change in building area, building height, use or exterior appearances.
Permit Issued
Issued on 2/15/2024
Issuing Office
San Pedro
Current Status
Permit Finaled on 10/29/2024

Permit Application Status History

Submitted 12/11/2023 APPLICANT
Assigned to Plan Check Engineer 12/14/2023 RICHARD GARCIA
Corrections Issued 12/14/2023 RICHARD GARCIA
Building Plans Picked Up 12/18/2023 APPLICANT
Plan Check Approved 12/28/2023 CAROLEAN BASMA
Issued 2/15/2024 APPLICANT
Permit Finaled 10/29/2024 FARHAD DADBIN

Permit Application Clearance Information

Tenant Habitability Plan Cleared 12/26/2023 HUGO GARRIDO GARZA

Contact Information

Contractor L & E Assets Inc; Lic. No.: 946841-B 23352 PERALTA DR UNIT 8      LAGUNA HILLS, CA 92653
Engineer Erstad,, Gerald Lee; Lic. No.: S4470 3463 OCEAN VIEW BLVD      GLENDALE, CA 91208

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 5/6/2024 Corrections Issued FARHAD DADBIN
Wood Frame 6/20/2024 Partial Approval RICARDO ROBLES
Wood Frame 7/9/2024 Not Ready for Inspection FARHAD DADBIN
Wood Frame 7/16/2024 Approved RICARDO ROBLES
Insulation 7/18/2024 Approved FARHAD DADBIN
Drywall Nailing 7/23/2024 Not Ready for Inspection FARHAD DADBIN
Drywall Nailing 7/29/2024 Approved CASIMIR BRITTON
Drywall Nailing 8/9/2024 Approved AMANUEL BERHE
Interior/Exterior Lathing 8/21/2024 Partial Approval FARHAD DADBIN
Final 9/30/2024 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 9/30/2024 Not Ready for Inspection FARHAD DADBIN
Final 10/3/2024 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 10/3/2024 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 10/3/2024 Not Ready for Inspection FARHAD DADBIN
Final 10/29/2024 Permit Finaled FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Approved FARHAD DADBIN
Smoke Detectors 10/29/2024 Approved FARHAD DADBIN