5958 3/4 W GUTHRIE AVE 90034

Certificate Information: 5958 3/4 W GUTHRIE AVE 90034

Application / Permit
23016-30000-42063
Plan Check / Job No.
B23WL02926
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of Garage (accessory to an apartment) at rear of the lot to an accessory Dwelling unit per LAMC 12.22 A.33 (c)-(d). All work per Wood Frame Prescriptive Provisions
Permit Issued
Issued on 6/27/2024
Issuing Office
West Los Angeles
Current Status
CofO in Progress on 3/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/30/2023 APPLICANT
Assigned to Plan Check Engineer 12/6/2023 RICHARD GARCIA
Corrections Issued 12/6/2023 RICHARD GARCIA
Building Plans Picked Up 12/7/2023 APPLICANT
Plan Check Approved 5/2/2024 EDWIN ESPIN
Issued 6/27/2024 APPLICANT
CofO in Progress 3/4/2025 ARTHUR NEGRETE
No Progress 3/30/2025 DEROLD HAUFF
CofO in Progress 3/30/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/18/2023 DAVID LOPEZ
Sewer availability Cleared 12/18/2023 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 12/19/2023 JUSTIN BICOL
Construction near power lines Cleared 3/27/2024 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/2/2024 Partial Approval SCOTT FINNILA
Deputy Drilled-In Anchors 7/19/2024 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/24/2024 Partial Approval SCOTT FINNILA
PLUMBING-Rough 8/16/2024 Approved SCOTT FINNILA
Rough-Elec/Plmb/HVAC 8/16/2024 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 9/9/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 9/9/2024 Approved ARTHUR NEGRETE
Green Building Rough 9/9/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 9/9/2024 Approved ARTHUR NEGRETE
Rough-Elec/Plmb/HVAC 9/9/2024 Approved ARTHUR NEGRETE
Green Building Final 9/13/2024 Partial Approval ARTHUR NEGRETE
Insulation 9/13/2024 Approved ARTHUR NEGRETE
Drywall Nailing 9/20/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 9/20/2024 Approved ARTHUR NEGRETE
Shower Pan 9/20/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 11/8/2024 Partial Inspection RONNIE MINDANAO
Final 11/8/2024 Partial Inspection RONNIE MINDANAO
Green Building Final 11/8/2024 Partial Inspection RONNIE MINDANAO
HVAC-Final 11/8/2024 Partial Inspection RONNIE MINDANAO
PLUMBING-Final 11/8/2024 Partial Inspection RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Not Ready RONNIE MINDANAO
Service/Power Release 11/8/2024 Partial Inspection RONNIE MINDANAO
Sewer 11/8/2024 Not Ready for Inspection RONNIE MINDANAO
Smoke Detectors 11/8/2024 Partial Inspection RONNIE MINDANAO
ELECTRICAL-Final 11/13/2024 Not Ready for Inspection ARTHUR NEGRETE
Final 11/13/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 11/13/2024 Approved ARTHUR NEGRETE
HVAC-Final 11/13/2024 Not Ready for Inspection ARTHUR NEGRETE
PLUMBING-Final 11/13/2024 Not Ready for Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 11/13/2024 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 11/13/2024 Not Ready for Inspection ARTHUR NEGRETE
Sewer 11/13/2024 Approved ARTHUR NEGRETE
Smoke Detectors 11/13/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 12/20/2024 Approved ARTHUR NEGRETE
Final 12/20/2024 Corrections Issued ARTHUR NEGRETE
HVAC-Final 12/20/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 12/20/2024 Approved ARTHUR NEGRETE
Service/Power Release 12/20/2024 Not Ready for Inspection ARTHUR NEGRETE
Final 12/31/2024 Partial Approval ARTHUR NEGRETE
Service/Power Release 12/31/2024 Approved ARTHUR NEGRETE
Final 2/28/2025 OK to Issue CofO ARTHUR NEGRETE