2320 1/2 S WALNUT AVE 90291
Certificate Information: 2320 1/2 S WALNUT AVE 90291
- Application / Permit
- 23016-30000-40983
- Plan Check / Job No.
- B23WL02878
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO A 456 SF ADU PER GCS 65852.2(e)(1)(A) and WFPP. COMPLY WITH DEPARTMENT ORDER effective date 10/03/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 2/20/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/20/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2023 | JASON JANGADA |
| Corrections Issued | 11/26/2023 | JASON JANGADA |
| Building Plans Picked Up | 12/14/2023 | APPLICANT |
| Applicant returned to address corrections | 12/19/2023 | CAROLEAN BASMA |
| Applicant returned to address corrections | 2/15/2024 | CAROLEAN BASMA |
| Plan Check Approved | 2/20/2024 | ALFREDO JARA |
| Issued | 2/20/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2023 | DARIN LAM |
| Sewer availability | Cleared | 12/22/2023 | DARIN LAM |
| Specific Plan | Cleared | 2/8/2024 | FREDDY GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/21/2024 | Approved | RYAN BARNES |
| Shower Pan | 4/12/2024 | Approved | RYAN BARNES |
| ELECTRICAL-Rough | 4/25/2024 | Approved | RYAN BARNES |
| HVAC-Rough | 4/25/2024 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 4/25/2024 | Approved | RYAN BARNES |
| PLUMBING-Rough | 4/25/2024 | Corrections Issued | RYAN BARNES |
| Insulation | 4/29/2024 | Approved | RYAN BARNES |
| Drywall Nailing | 5/1/2024 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 6/5/2024 | Approved | RYAN BARNES |
| Final | 6/5/2024 | Conditional Approval | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 6/5/2024 | Approved | RYAN BARNES |