3553 S BEETHOVEN ST 90066

Certificate Information: 3553 S BEETHOVEN ST 90066

Application / Permit
23016-30000-35511
Plan Check / Job No.
B23WL02561
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion and addition of existing detached garage to an ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 2/9/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 YASHAR EMAMI
Corrections Issued 10/16/2023 YASHAR EMAMI
Quality Review Completed 10/19/2023 REZA HAGHIGHAT
Building Plans Picked Up 10/23/2023 APPLICANT
Plan Check Approved 2/2/2024 YASHAR EMAMI
Plan Check Approved 2/8/2024 YASHAR EMAMI
Issued 2/9/2024 APPLICANT
CofO in Progress 8/27/2024 DAVID FEILER
Permit Finaled 8/29/2024 RICHARD STEINBACH
CofO Issued 8/29/2024 RICHARD STEINBACH
Permit Finaled 8/29/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/29/2023 ANDREA SAINT-ANTONIN
Eng Process Fee Ord 176,300 Cleared 11/29/2023 ANDREA SAINT-ANTONIN
Sewer availability Cleared 11/29/2023 ANDREA SAINT-ANTONIN
"Q" conditions Cleared 12/6/2023 SPENCER WEJROWSKI
Low Impact Development (LID) Cleared 12/14/2023 ROGELIO CORTES
Specific Plan Cleared 12/18/2023 FREDDY GARCIA
Roof/Waste drainage to street Cleared 1/4/2024 KIMBERLY HERNANDEZ
Construction near power lines Cleared 1/29/2024 RIDWAN HARDY
GPI Written Notices Cleared 2/2/2024 YASHAR EMAMI
Grading Pre-Inspection Cleared 2/2/2024 YASHAR EMAMI

Contact Information

Architect Avila,, Tom A; Lic. No.: C28086 3304 PICO BLVD # G      SANTA MONICA, CA 90405
Contractor Liebobuilders; Lic. No.: 1054050-B 18401 BURBANK BLVD SUITE 120      TARZANA, CA 91356
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/16/2024 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 2/23/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Conditional Approval TEMISTOCLES CAAL
HVAC-Rough 3/29/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 3/29/2024 Partial Approval TEMISTOCLES CAAL
Sewer 3/29/2024 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 4/1/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/1/2024 Conditional Approval JESUS RODRIGUEZ
HVAC-Rough 4/1/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 4/1/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/8/2024 Approved TEMISTOCLES CAAL
Shower Pan 4/8/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 4/18/2024 Approved JESUS RODRIGUEZ
Insulation 4/22/2024 Corrections Issued JESUS RODRIGUEZ
Insulation 4/26/2024 Not Ready for Inspection JESUS RODRIGUEZ
Wood Frame 4/26/2024 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/3/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 5/3/2024 Approved JESUS RODRIGUEZ
Green Building Rough 5/3/2024 Approved JESUS RODRIGUEZ
Insulation 5/3/2024 Approved JESUS RODRIGUEZ
Final 8/19/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 8/19/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 8/19/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/19/2024 SGSOV Not Required JESUS RODRIGUEZ
Smoke Detectors 8/19/2024 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Final 8/22/2024 Approved HERBERT GIRON
Final 8/22/2024 Corrections Issued HERBERT GIRON
Green Building Final 8/22/2024 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 8/22/2024 Approved HERBERT GIRON
Final 8/23/2024 OK to Issue CofO HERBERT GIRON
Green Building Final 8/23/2024 Approved HERBERT GIRON
HVAC-Final 8/23/2024 Approved HERBERT GIRON
Service/Power Release 8/23/2024 Approved HERBERT GIRON