850 N TOYOPA DR 90272
Certificate Information: 850 N TOYOPA DR 90272
- Application / Permit
- 23016-30000-32213
- Plan Check / Job No.
- B23WL02353
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (E) Single family dwelling. No change to (E) building footprint.
- Permit Issued
- Issued on 10/27/2023
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 12/23/2024
Permit Application Status History
| Submitted | 9/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2023 | RICHARD GARCIA |
| Corrections Issued | 9/27/2023 | RICHARD GARCIA |
| Plan Check Approved | 10/18/2023 | ALFREDO JARA |
| Issued | 10/27/2023 | APPLICANT |
| Permit Finaled | 12/23/2024 | EVAN COOPER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/6/2023 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/6/2023 | Corrections Issued | EVAN COOPER |
| Deputy Drilled-In Anchors | 11/13/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/14/2023 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 2/22/2024 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 3/5/2024 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 3/5/2024 | Approved | EVAN COOPER |
| HVAC-Rough | 3/5/2024 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 3/5/2024 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 3/7/2024 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 3/7/2024 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 3/7/2024 | Approved | EVAN COOPER |
| HVAC-Rough | 3/13/2024 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/13/2024 | Partial Approval | EVAN COOPER |
| Insulation | 4/8/2024 | Corrections Issued | EVAN COOPER |
| Underground Mechanical | 4/8/2024 | Partial Approval | EVAN COOPER |
| Insulation | 4/9/2024 | Not Ready for Inspection | HERBERT GIRON |
| Drywall Nailing | 4/23/2024 | Approved | EVAN COOPER |
| Insulation | 4/23/2024 | Approved | EVAN COOPER |
| Final | 12/4/2024 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/4/2024 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 12/4/2024 | Approved | EVAN COOPER |
| Final | 12/23/2024 | Permit Finaled | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Approved | EVAN COOPER |