8326 S MCCONNELL AVE 90045
Certificate Information: 8326 S MCCONNELL AVE 90045
- Application / Permit
- 23016-30000-32115
- Plan Check / Job No.
- B23WL02350
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Detached garage at rear of lot conversion to ADU per CA Govt. Code 65852.2(e)(1)(A) *All construction per WFPP*
- Permit Issued
- Issued on 10/11/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2023 | RICHARD GARCIA |
| Corrections Issued | 9/23/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 9/27/2023 | APPLICANT |
| Applicant returned to address corrections | 10/3/2023 | AMY GUEVARRA |
| Plan Check Approved | 10/11/2023 | AMY GUEVARRA |
| Issued | 10/11/2023 | APPLICANT |
| CofO in Progress | 6/13/2024 | BOBBY KEY |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
| CofO Issued | 6/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/29/2023 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2023 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 9/29/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/29/2023 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 10/10/2023 | MOHAMMAD HASAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/16/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 10/30/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 10/30/2023 | Partial Approval | BOBBY KEY |
| Sewer | 10/30/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 11/27/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 11/27/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 11/30/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 11/30/2023 | Approved | BOBBY KEY |
| Sewer | 11/30/2023 | Approved | BOBBY KEY |
| Insulation | 12/5/2023 | Corrections Issued | TEMISTOCLES CAAL |
| Shower Pan | 12/5/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 12/7/2023 | Corrections Issued | TEMISTOCLES CAAL |
| Insulation | 12/7/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Sewer | 12/11/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 12/13/2023 | Conditional Approval | MICHAEL PELHAM |
| HVAC-Final | 12/13/2023 | Corrections Issued | TEMISTOCLES CAAL |
| Insulation | 12/13/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 12/21/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/21/2023 | Approved | BOBBY KEY |
| Gas Test | 3/27/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Final | 3/27/2024 | Not Ready for Inspection | BOBBY KEY |
| Underground Mechanical | 3/27/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 5/2/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 5/2/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/2/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/6/2024 | Approved | BOBBY KEY |
| Final | 6/6/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 6/6/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 6/6/2024 | Approved | BOBBY KEY |
| Final | 6/13/2024 | OK to Issue CofO | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/13/2024 | SGSOV Approved | BOBBY KEY |