532 N KILKEA DR 90048

Certificate Information: 532 N KILKEA DR 90048

Application / Permit
23016-30000-28633
Plan Check / Job No.
B23WL02127
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ADU PER GCS 65852.2 (e)(1)(A)
Permit Issued
Issued on 10/4/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2023 APPLICANT
Assigned to Plan Check Engineer 8/28/2023 JOHNPAUL ISIP
Corrections Issued 8/28/2023 JOHNPAUL ISIP
Building Plans Picked Up 9/6/2023 APPLICANT
Plan Check Approved 10/4/2023 ALFREDO JARA
Issued 10/4/2023 APPLICANT
CofO in Progress 3/26/2024 AMIR NAZARIAN
Permit Finaled 3/29/2024 DEROLD HAUFF
CofO Issued 3/29/2024 DEROLD HAUFF
Permit Finaled 3/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/3/2023 TREVOR QUAN
Sewer availability Cleared 10/3/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 10/4/2023 TREVOR QUAN

Contact Information

Architect Weaver,, Henry Allen; Lic. No.: C21887 11702 8TH AVENUE NW      SEATTLE, WA 98177
Contractor Owner-Builder       ,
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/6/2023 Approved LILIANA PORTILLO
Footing/Foundation/Slab 10/6/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 10/31/2023 Off-Hour Fees Due
PLUMBING-Rough 11/1/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 11/7/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 11/7/2023 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 11/14/2023 Not Ready for Inspection LILIANA PORTILLO
METHANE-Rough 11/14/2023 Approved LILIANA PORTILLO
Underground Mechanical 11/17/2023 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 11/27/2023 Corrections Issued LILIANA PORTILLO
Green Building Rough 11/27/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 11/27/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 11/27/2023 Corrections Issued LILIANA PORTILLO
Shower Pan 11/27/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 12/4/2023 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 12/4/2023 Approved LILIANA PORTILLO
HVAC-Rough 12/4/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 12/4/2023 Approved LILIANA PORTILLO
Green Building Rough 12/7/2023 Not Ready for Inspection LILIANA PORTILLO
Insulation 12/7/2023 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 12/12/2023 Approved LILIANA PORTILLO
Green Building Rough 12/12/2023 Approved LILIANA PORTILLO
Insulation 12/12/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/12/2023 Partial Approval LILIANA PORTILLO
Deputy Wood Construction 12/20/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Approved LILIANA PORTILLO
Sewer 12/20/2023 Corrections Issued LILIANA PORTILLO
Drywall Nailing 12/28/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/28/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 2/12/2024 Not Ready for Inspection AMIR NAZARIAN
Special/Order Compliance 2/12/2024 Partial Approval JOAQUIN GREENOUGH
Service/Power Release 2/14/2024 Partial Inspection AMIR NAZARIAN
ELECTRICAL-Final 2/28/2024 Approved AMIR NAZARIAN
Final 2/28/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 2/28/2024 Not Ready for Inspection AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 2/28/2024 SGSOV Approved AMIR NAZARIAN
Service/Power Release 2/28/2024 Approved AMIR NAZARIAN
Smoke Detectors 2/28/2024 Not Ready for Inspection AMIR NAZARIAN
Special/Order Compliance 2/28/2024 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Final 3/1/2024 Corrections Issued AMIR NAZARIAN
Sewer 3/1/2024 Not Ready for Inspection AMIR NAZARIAN
Special/Order Compliance 3/1/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Final 3/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 3/16/2024 Not Ready for Inspection ALEJANDRO DE ARTOLA
Smoke Detectors 3/16/2024 Not Ready for Inspection ALEJANDRO DE ARTOLA
Final 3/19/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 3/19/2024 Approved AMIR NAZARIAN
Service/Power Release 3/19/2024 Approved AMIR NAZARIAN
Smoke Detectors 3/19/2024 Approved AMIR NAZARIAN
Final 3/22/2024 OK to Issue CofO AMIR NAZARIAN