9025 W 25TH ST 90034
Certificate Information: 9025 W 25TH ST 90034
- Application / Permit
- 23016-30000-27135
- Plan Check / Job No.
- B23WL02058
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/31/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2023 | JOHNPAUL ISIP |
| Corrections Issued | 8/20/2023 | JOHNPAUL ISIP |
| Building Plans Picked Up | 8/23/2023 | APPLICANT |
| Plan Check Approved | 9/21/2023 | JOHNPAUL ISIP |
| Issued | 1/31/2024 | APPLICANT |
| CofO in Progress | 10/10/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
| CofO Issued | 10/15/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/1/2023 | RUSSELL BONVOULOIR |
| Address approval | Cleared | 9/2/2023 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/2/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 9/2/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2023 | ADRIAN SANCHEZ |
| Construction within easement | Cleared | 9/19/2023 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/13/2024 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 4/19/2024 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 4/19/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 4/30/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/1/2024 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 5/31/2024 | Partial Approval | MEL KHACHATOURIAN |
| Wood Frame | 6/26/2024 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 7/5/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 7/5/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 7/5/2024 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 7/5/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 7/16/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 7/16/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 7/16/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 7/16/2024 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 7/16/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 7/19/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 7/19/2024 | Partial Approval | MEL KHACHATOURIAN |
| Shower Pan | 7/19/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Drywall Nailing | 7/24/2024 | Approved | KIRK SANDERS |
| Shower Pan | 7/24/2024 | Approved | KIRK SANDERS |
| Underground Mechanical | 7/24/2024 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 7/29/2024 | Approved | MEL KHACHATOURIAN |
| Final | 10/1/2024 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 10/1/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 10/1/2024 | Approved | ARAM AVEDISIAN |
| Final | 10/7/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 10/7/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Final | 10/9/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| Service/Power Release | 10/11/2024 | Approved | MEL KHACHATOURIAN |