2107 S CAMDEN AVE 90025
Certificate Information: 2107 S CAMDEN AVE 90025
- Application / Permit
- 23016-30000-24408
- Plan Check / Job No.
- B23WL01882
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel of Existing Single Family Dwelling Including Kitchen And Bathrooms And New Rear Addition At Rear Of S.F.D. To Create New Patio Cover.
- Permit Issued
- Issued on 8/25/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2023 | JAHANSHAH POURHASSAN |
| Corrections Issued | 7/29/2023 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 8/14/2023 | DAVID CASTILLO |
| Plan Check Approved | 8/18/2023 | EDWIN ESPIN |
| Issued | 8/25/2023 | APPLICANT |
| CofO in Progress | 11/8/2024 | KIRK SANDERS |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
| CofO Issued | 11/19/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/11/2023 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 8/14/2023 | DARIN LAM |
Contact Information
| Contractor | Calcons Inc; Lic. No.: 1077157-B | 9400 CATTARAUGUS AVE LOS ANGELES, CA 90034 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/28/2023 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 8/30/2023 | Corrections Issued | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 8/30/2023 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 9/15/2023 | Approved | TEMISTOCLES CAAL |
| Deputy Reinf. Concrete | 9/18/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 9/18/2023 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 9/21/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 9/21/2023 | Corrections Issued | BEN MOLSTAD |
| Wood Frame | 9/21/2023 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 11/20/2023 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 11/20/2023 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/5/2023 | Conditional Approval | BEN MOLSTAD |
| Green Building Rough | 12/5/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 12/12/2023 | Conditional Approval | BEN MOLSTAD |
| Interior/Exterior Lathing | 12/12/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 1/8/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 1/16/2024 | Approved | BEN MOLSTAD |
| Deputy Drilled-In Anchors | 2/12/2024 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 5/10/2024 | Approved | MEL KHACHATOURIAN |
| Final | 5/10/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 5/10/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 5/10/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 5/10/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Deputy Wood Construction | 6/4/2024 | Conditional Approval | KIRK SANDERS |
| Final | 6/4/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 6/4/2024 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 6/4/2024 | Approved | KIRK SANDERS |
| Final | 10/23/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 10/23/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Approved | KIRK SANDERS |
| Final | 10/24/2024 | Corrections Issued | KIRK SANDERS |
| Final | 11/7/2024 | OK to Issue CofO | KIRK SANDERS |