1345 N CHAUTAUQUA BLVD 90272

Certificate Information: 1345 N CHAUTAUQUA BLVD 90272

Application / Permit
23016-30000-20025
Plan Check / Job No.
B23WL01600
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior Structural Remodel to (E)2 story Single Family Dwelling W/ Basement, scope of work to include: New bedroom, new retaining wall in crawl space and new stairs leading to basement.
Permit Issued
Issued on 9/19/2023
Issuing Office
West Los Angeles
Current Status
Issued on 9/19/2023

Permit Application Status History

Submitted 6/16/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 RICHARD GARCIA
Corrections Issued 6/24/2023 RICHARD GARCIA
Building Plans Picked Up 6/27/2023 APPLICANT
Plan Check Approved 7/11/2023 EDWIN ESPIN
Issued 9/19/2023 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 7/6/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/7/2023 DINAH GARIN
Grading Pre-Inspection Cleared 7/11/2023 RICHARD GARCIA

Contact Information

Architect Trujillo,, Sean Samuel; Lic. No.: C29830 4464 VIA ACIANDO      CAMARILLO, CA 93012
Contractor Iverson Construction Inc; Lic. No.: 281837-B 3719 ELKHORN CT      SIMI VALLEY, CA 93063
Engineer Tani,, Jason; Lic. No.: C58271 5296 VIA PATRICIA      THOUSAND OAKS, CA 91320

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/19/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/23/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 10/24/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 11/7/2023 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 11/8/2023 Partial Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 11/9/2023 Conditional Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 11/16/2023 Conditional Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 11/17/2023 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 11/17/2023 Partial Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 11/20/2023 Conditional Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 12/8/2023 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 12/18/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 1/2/2024 Partial Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 1/3/2024 Conditional Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 1/3/2024 Conditional Approval ARAM AVEDISIAN
PLUMBING-Rough 4/4/2024 Approved ARAM AVEDISIAN
Wood Frame 5/8/2024 Partial Inspection KENNETH NAGLE
Drywall Nailing 5/22/2024 Partial Approval ARAM AVEDISIAN
HVAC-Rough 7/3/2024 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Corrections Issued ARAM AVEDISIAN
Shower Pan 7/22/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Partial Approval EVAN COOPER
HVAC-Rough 8/28/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/28/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 9/4/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/9/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Approved JESUS RODRIGUEZ
Insulation 9/18/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 10/8/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 11/4/2024 Partial Approval ARAM AVEDISIAN