4709 S LINDBLADE DR 90230
Certificate Information: 4709 S LINDBLADE DR 90230
- Application / Permit
- 23016-30000-19267
- Plan Check / Job No.
- B23WL01545
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO A NEW DETACHED ADU PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 11/22/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2023 | JOHNPAUL ISIP |
| Corrections Issued | 6/20/2023 | JOHNPAUL ISIP |
| Building Plans Picked Up | 6/22/2023 | APPLICANT |
| Plan Check Approved | 11/20/2023 | CAROLEAN BASMA |
| Issued | 11/22/2023 | APPLICANT |
| CofO in Progress | 9/23/2024 | JESUS PINEDA |
| Permit Finaled | 9/24/2024 | RICHARD STEINBACH |
| CofO Issued | 9/24/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/24/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/20/2023 | LIAM ODONOVAN |
| Sewer availability | Cleared | 7/20/2023 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2023 | LIAM ODONOVAN |
| Specific Plan | Cleared | 8/15/2023 | EDUARDO HERMOSO |
| Construction near power lines | Cleared | 11/14/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/4/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Pre-Inspection | 2/1/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 4/3/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/3/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/15/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/22/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/30/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 4/30/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 5/10/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Special/Order Compliance | 5/10/2024 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/14/2024 | Partial Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 5/14/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2024 | Partial Approval | JESUS RODRIGUEZ |
| Insulation | 5/16/2024 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/6/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/1/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/1/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 7/1/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 7/1/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 7/1/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/1/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/6/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 9/6/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 9/18/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 9/18/2024 | Approved | JESUS PINEDA |
| Insulation | 9/18/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 9/20/2024 | Approved | JESUS PINEDA |
| Final | 9/20/2024 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 9/20/2024 | Approved | JESUS PINEDA |
| Smoke Detectors | 9/20/2024 | Approved | JESUS PINEDA |