4709 S LINDBLADE DR 90230

Certificate Information: 4709 S LINDBLADE DR 90230

Application / Permit
23016-30000-19267
Plan Check / Job No.
B23WL01545
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO A NEW DETACHED ADU PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 11/22/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2023 APPLICANT
Assigned to Plan Check Engineer 6/16/2023 JOHNPAUL ISIP
Corrections Issued 6/20/2023 JOHNPAUL ISIP
Building Plans Picked Up 6/22/2023 APPLICANT
Plan Check Approved 11/20/2023 CAROLEAN BASMA
Issued 11/22/2023 APPLICANT
CofO in Progress 9/23/2024 JESUS PINEDA
Permit Finaled 9/24/2024 RICHARD STEINBACH
CofO Issued 9/24/2024 RICHARD STEINBACH
Permit Finaled 9/24/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/20/2023 LIAM ODONOVAN
Sewer availability Cleared 7/20/2023 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 7/24/2023 LIAM ODONOVAN
Specific Plan Cleared 8/15/2023 EDUARDO HERMOSO
Construction near power lines Cleared 11/14/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/4/2024 Partial Inspection TEMISTOCLES CAAL
Pre-Inspection 2/1/2024 Not Ready for Inspection JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/3/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 4/3/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 4/15/2024 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 4/22/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 4/30/2024 Not Ready for Inspection JESUS RODRIGUEZ
Green Building Rough 4/30/2024 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 5/10/2024 Not Ready for Inspection JESUS RODRIGUEZ
Special/Order Compliance 5/10/2024 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/14/2024 Partial Inspection JESUS RODRIGUEZ
Green Building Rough 5/14/2024 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 Partial Approval JESUS RODRIGUEZ
Insulation 5/16/2024 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 6/6/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/1/2024 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 7/1/2024 Corrections Issued JESUS RODRIGUEZ
Final 7/1/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 7/1/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 7/1/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 7/1/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 9/6/2024 Corrections Issued BOBBY KEY
HVAC-Rough 9/6/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 9/18/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Approved JESUS PINEDA
HVAC-Rough 9/18/2024 Approved JESUS PINEDA
Insulation 9/18/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 9/20/2024 Approved JESUS PINEDA
Final 9/20/2024 OK to Issue CofO JESUS PINEDA
Green Building Final 9/20/2024 Approved JESUS PINEDA
Smoke Detectors 9/20/2024 Approved JESUS PINEDA