827 E SUPERBA AVE 90291

Certificate Information: 827 E SUPERBA AVE 90291

Application / Permit
23016-30000-16261
Plan Check / Job No.
B23WL01332
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) Detached Garage to an Accessory Dwelling Unit w/ addition per state code in Venice specific plan. COMPLY WITH DEPARTMENT ORDER effective date 02/17/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. CEIS Case Number is 976822.
Permit Issued
Issued on 8/21/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/24/2023 RICHARD GARCIA
Corrections Issued 5/24/2023 RICHARD GARCIA
Building Plans Picked Up 5/31/2023 APPLICANT
Applicant returned to address corrections 2/25/2025 AMY GUEVARRA
Plan Check Approved 5/22/2025 AMY GUEVARRA
Issued 8/21/2025 APPLICANT
Permit Finaled 4/13/2026 CLAUDIO MORENO
CofO Issued 4/13/2026 CLAUDIO MORENO
Permit Finaled 4/13/2026 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 1/22/2024 ANDREA SAINT-ANTONIN
Eng Process Fee Ord 176,300 Cleared 1/22/2024 ANDREA SAINT-ANTONIN
Roof/Waste drainage to street Cleared 1/22/2024 ANDREA SAINT-ANTONIN
Sewer availability Cleared 1/22/2024 ANDREA SAINT-ANTONIN
Coastal Zone Cleared 4/14/2025 JAZMIN ROQUE
Specific Plan Cleared 4/16/2025 JAZMIN ROQUE
Specific Plan Cleared 5/20/2025 PEDRO AYALA

Contact Information

Architect Bambrough,, Patrick; Lic. No.: C34299 1590 ANDERSON AVE. APT 5J      FORT LEE, NJ 07024
Architect Zubieta,, Carlos M; Lic. No.: C33074 1745 ABBOT KINNEY BLVD 2ND FLOOR      VENICE, CA 90291
Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/25/2025 Approved RYAN BARNES
Footing/Foundation/Slab 9/15/2025 Not Ready for Inspection RYAN BARNES
Wood Frame 9/26/2025 Partial Approval RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Partial Inspection RYAN BARNES
Insulation 10/6/2025 Partial Approval RYAN BARNES
ELECTRICAL-Rough 10/20/2025 Corrections Issued RYAN BARNES
Excavation/Setback/Form/Re-Bar 10/20/2025 Approved RYAN BARNES
ELECTRICAL-Rough 10/22/2025 Approved RYAN BARNES
Green Building Rough 10/23/2025 Approved RYAN BARNES
Wood Frame 10/24/2025 Partial Approval RYAN BARNES
PLUMBING-Rough 10/27/2025 Approved RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Approved RYAN BARNES
Interior/Exterior Lathing 10/30/2025 Approved RYAN BARNES
BUILDING-Rough-Frame 11/20/2025 Approved RYAN BARNES
Final 11/20/2025 Corrections Issued RYAN BARNES
Green Building Final 11/20/2025 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 11/20/2025 SGSOV Approved RYAN BARNES
Smoke Detectors 11/20/2025 Approved RYAN BARNES
Final 12/11/2025 Conditional Approval RYAN BARNES