727-729 E 27TH ST 90011
Certificate Information: 727-729 E 27TH ST 90011
- Application / Permit
- 23016-30000-15675
- Plan Check / Job No.
- B23WL01275
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Addition of bathroom in each unit of a (E) duplex. All work interior only.
- Permit Issued
- Issued on 6/20/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/3/2023
Permit Application Status History
| Submitted | 5/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2023 | ALFREDO JARA |
| Corrections Issued | 5/15/2023 | ALFREDO JARA |
| Plan Check Approved | 6/12/2023 | ALFREDO JARA |
| Issued | 6/20/2023 | APPLICANT |
| Permit Finaled | 11/2/2023 | ALEJANDRO DE ARTOLA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/14/2023 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 7/14/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 7/14/2023 | Not Ready for Inspection | JOHN KLARIN |
| Wood Frame | 7/19/2023 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 8/16/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/16/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 10/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/17/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/17/2023 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 10/17/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/24/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/24/2023 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 10/24/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 11/1/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/2/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/2/2023 | Permit Finaled | ALEJANDRO DE ARTOLA |